This newsletter discusses the impact of COVID-19 lockdowns on the construction industry and conferences. It also summarizes recent cases supporting the use of adjudication when a party is in liquidation. Additionally, it examines the complex issue of recovering party costs in adjudication proceedings, with the current prohibition on such awards potentially limiting access to adjudication for those who need it most. The newsletter argues that allowing recovery of party costs as interest in some late payment cases could help balance competing statutory requirements while extending key rights to the construction industry.
1. The document discusses the development of security of payment legislation (SOPL) and contractual adjudication in Hong Kong construction projects. It outlines key milestones in SOPL's development from 2001 to the present and proposed additions to public works contracts to facilitate timely processing of payments.
2. It summarizes recent developments in contractual adjudication, including requirements for payment responses, conditional payment provisions, and adjudicator decisions. Adjudicators would be appointed by adjudication nominating bodies under proposed legislation.
3. The document presents draft articles related to adjudication procedures, including appointment of adjudicators, payment claims, withdrawal of adjudication, and eligibility of adjudicators. It focuses on preventing "
The document discusses key aspects and opportunities provided by the Insolvency and Bankruptcy Code, 2016 (IBC) in India:
- IBC provides a timely resolution process for lenders to preserve the value of borrowers' businesses while controlling the process. It avoids value destruction caused by delays.
- Resolution is a business decision made by lenders, with an adjudicator only overseeing the process. IBC distinguishes between business failure and malfeasance.
- Creditors are in control and must manage the business during resolution. Insolvency professionals drive the process and need support from accounting, legal and business professionals to maximize value.
- IBC aims to create an '
This document provides summaries of 11 key questions regarding the Insolvency and Bankruptcy Code of 2016 in India. It discusses issues like whether appeals can only be filed by directors, what constitutes a dispute for rejecting operational creditor applications, whether the timeline requirements are mandatory or not, and whether personal guarantees can be enforced during corporate insolvency resolution processes. The document aims to clarify common queries around implementing and interpreting various aspects of the IBC 2016 legislation.
This document summarizes recent tax law amendments in Zimbabwe. It discusses changes to provisions around related party expenditures, permanent establishments, taxable income attributable to PEs, capital gains tax, classification of goods, and reporting of unprofessional conduct. Key points include broadening the capital gains tax base, classifying goods based on tariff headings and chapter notes, and allowing the tax authority to report professionals for actions aimed at tax evasion.
UK Adjudicators are the largest multi-disciplinary adjudicator nominating panel in the United Kingdom.
We offer free adjudicator nominations and also a capped fee scheme
Rethinking the IDR Requirement As It Applies to Energy Mining O&G Companies ...
It has not taken long for the inevitable confusion and pushback, in respect of the recent imposition by Bank Indonesia (“BI”) of a requirement to use the Indonesian Rupiah (“IDR”) for all domestic transactions (“IDR equirement”), to make itself felt.
Case study: Essar Steel - Insolvency Resolution Plan
Objectives & Agenda :
The primary objective of Insolvency and Bankruptcy Code (IBC) is the resolution of distressed assets of the insolvent debtor in a time bound structured manner and to enable such insolvent entity to continue as a going concern. IBC emerges as a fast track mechanism in completion of insolvency proceedings and aims at maximising the value of the assets of an insolvent entity. The Supreme Court judgement on Essar Steel is a landmark judgement that affirms the principles of IBC. The webinar analyses the key aspects of the judgments delivered by all the judicial forums viz. National Company Law Tribunal (NCLT), National Company Law Appellate Tribunal (NCLAT) and the Honourable Supreme Court in Essar Steel case.
This presentation discusses the question as to whether a statute on mediation is required to be enacted in India. It argues that an ADR code has to be enacted so that dispute and its resolution are seen holistically.
The document discusses the rules of statutory interpretation applied to tax statutes based on a case cited. It provides the background and context for the rules. The key rules discussed are:
1) Words are given their ordinary meaning and courts do not consider consequences of interpretation or imply meanings not clearly stated.
2) Ambiguities or doubts are resolved in favor of the taxpayer.
3) The "golden rule" allows considering consequences to avoid absurdity if the language permits.
4) The "mischief rule" allows considering reasons for legislation to advance its purpose if ambiguity exists.
More recent cases show a shift toward a more purposive approach seeking legislative intent over formalism. Courts now aim to
William Kosar What Every Budget Officer Should Know_Rwanda
This document provides an overview of key contract information for budget officers. It discusses types of contracts including public contracts, general conditions of contracts, and public-private partnerships. It also covers memorandums of understanding, performance guarantees, bid rigging, and types of resource exploration contracts like production sharing agreements and power purchase agreements. Checklists are recommended to ensure all important contract details are included. The dangers of memorandums of understanding being non-binding are outlined, and performance guarantees using letters of credit or bonds are described. Finally, common forms of bid rigging like cover bidding, bid suppression, bid rotation, and market allocation are defined, along with warning signs of anti-competitive bidding practices.
Today, with us we have “Mr. Ashok Juneja” who is an Advocate and Insolvency Professional. He is Founder & Managing Partner of a multi disciplinary Law Firm “MANTRAH LAW HOUSE LLP” which is an LLP of renowned Mantrah Group)
He is also director of “MANTRAH INSOLVENCY PROFESSIONALS PVT LTD”
Mr. Juneja, aged about 63 years, is a Law Graduate, Company Secretary, Cost Accountant, M.Com. Mr. Juneja also holds Diploma in Business Finance (DBF), NSE Certification in Financial Market (NCFM) and Advance Diploma in Computer Application (ADICA) etc.
Mr Juneja, a graduate from one of the most prestigious college “Shri Ram College of Commerce” has an overall combined experience of more than 40 years in Corporate Laws including Appearances in Supreme Court, High Courts, National Company Law Tribunal (NCLT), National Company Law Appellate Tribunal (NCLAT), DRT etc.
Mr Juneja empanelled with State Bank of India and Andhra Bank as an Insolvency Professional has already handled assignments of Interim Resolution Professional (IRP), Resolution Professional (RP) and Voluntary Liquidator.
He is also member of Bar Council of Delhi, Executive Member of NCLT & NCLAT Bar Association, Bar Association of Supreme Court, Delhi High Court, Institute of Company Secretaries of India, Institute of Cost Accountant of India, CII, PHD Chamber of Commerce & Industry and ASSOCHAM.
He is also the Director on the board and Adviser to many Companies which include Public Listed Companies.
The document provides information about online training for landlords in Wales to become licensed under the Rent Smart Wales scheme. It outlines that the training is divided into 5 sections that cover topics relevant to managing rental properties legally. Learners can progress through modules at their own pace and there is a certificate awarded upon passing an assessment at the end of the course.
This document provides an overview of recent regulatory compliance updates that are relevant for insurance brokers in Australia. It discusses the key changes and requirements relating to the National Consumer Credit Protection Act 2009, compensation requirements for AFS licensees, potential refunds of stamp duty on insurance policies, disclosure of the Financial Claims Scheme, implications of double insurance provisions, proposed amendments to the Insurance Contracts Act, and new APRA data collection requirements for brokers. Compliance with the new credit licensing regime and responsible lending obligations is required if brokers provide credit assistance for premium funding.
Construction Adjudication for Professional Services Contract
This document discusses statutory adjudication in contracts for professional services in Hong Kong. It provides background on security of payment legislation in other countries and past surveys on payment practices. It then outlines key features of statutory adjudication, including that it provides a fast, inexpensive, and temporary binding dispute resolution process. The document discusses what types of contracts and construction activities would be covered under the proposed legislation in Hong Kong, including value thresholds. It also summarizes the adjudication procedure and rights around payment periods, suspensions for non-payment, and ineffective payment provisions.
Washington State legislative changes from 2011 (reciprocal bid preference law), 2012 (bills that passed and didn't pass), and 2013 (potential legislation affecting re-authorization of Alternative Public Works contracting.
The document summarizes the key changes made by the Building Industry Fairness (Security of Payment) and Other Legislation Amendment Act 2020 in Queensland, Australia:
1. It replaces the existing project bank account framework for Queensland government construction projects with a simplified statutory trust regime for payments to subcontractors and retention monies.
2. It increases the Queensland Building and Construction Commission's enforcement powers to monitor compliance with the new project trust requirements and introduces penalties for non-compliance.
3. For all construction contracts in Queensland, it establishes new offenses for principals and contractors who fail to pay certified or adjudicated amounts by the due date, with penalties of up to $13,345 for individuals and $66
Case Alert Aviva - Advocate General's opinionGraham Brearley
This document summarizes an opinion issued by an Advocate General of the Court of Justice of the European Union regarding the operation of cost sharing groups under EU VAT law. The Advocate General confirmed that in her view, the cost sharing group exemption is not available to businesses operating in different countries or those providing insurance services under Article 135 of the VAT Directive. The full court is still to issue its judgment in this case and the earlier DNB Banka case to determine whether VAT law imposes such restrictions.
This document discusses statutory and contractual adjudication in Hong Kong. It provides an overview of the development of security of payment legislation in Hong Kong, including reports and public consultations from 2001 to 2021. It outlines the application and requirements of the proposed security of payment legislation, including payment claim processes, maximum payment periods, adjudication procedures, and the adjudicator's jurisdiction. It also discusses recent proposals to implement aspects of security of payment in public works contracts prior to the enactment of legislation.
This chapter discusses rights of third parties in contracts including third-party beneficiary contracts, assignments, delegations, and novation. It defines key terms and concepts and outlines the general principles for each topic, including when consent is required from the original parties, the rights and obligations of assignees and delegates, and the requirements for a valid novation that discharges the original contract. The chapter also includes several case studies and critical thinking questions.
1. The document discusses the development of security of payment legislation (SOPL) and contractual adjudication in Hong Kong construction projects. It outlines key milestones in SOPL's development from 2001 to the present and proposed additions to public works contracts to facilitate timely processing of payments.
2. It summarizes recent developments in contractual adjudication, including requirements for payment responses, conditional payment provisions, and adjudicator decisions. Adjudicators would be appointed by adjudication nominating bodies under proposed legislation.
3. The document presents draft articles related to adjudication procedures, including appointment of adjudicators, payment claims, withdrawal of adjudication, and eligibility of adjudicators. It focuses on preventing "
The document discusses key aspects and opportunities provided by the Insolvency and Bankruptcy Code, 2016 (IBC) in India:
- IBC provides a timely resolution process for lenders to preserve the value of borrowers' businesses while controlling the process. It avoids value destruction caused by delays.
- Resolution is a business decision made by lenders, with an adjudicator only overseeing the process. IBC distinguishes between business failure and malfeasance.
- Creditors are in control and must manage the business during resolution. Insolvency professionals drive the process and need support from accounting, legal and business professionals to maximize value.
- IBC aims to create an '
This document provides summaries of 11 key questions regarding the Insolvency and Bankruptcy Code of 2016 in India. It discusses issues like whether appeals can only be filed by directors, what constitutes a dispute for rejecting operational creditor applications, whether the timeline requirements are mandatory or not, and whether personal guarantees can be enforced during corporate insolvency resolution processes. The document aims to clarify common queries around implementing and interpreting various aspects of the IBC 2016 legislation.
This document summarizes recent tax law amendments in Zimbabwe. It discusses changes to provisions around related party expenditures, permanent establishments, taxable income attributable to PEs, capital gains tax, classification of goods, and reporting of unprofessional conduct. Key points include broadening the capital gains tax base, classifying goods based on tariff headings and chapter notes, and allowing the tax authority to report professionals for actions aimed at tax evasion.
UK Adjudicators are the largest multi-disciplinary adjudicator nominating panel in the United Kingdom.
We offer free adjudicator nominations and also a capped fee scheme
It has not taken long for the inevitable confusion and pushback, in respect of the recent imposition by Bank Indonesia (“BI”) of a requirement to use the Indonesian Rupiah (“IDR”) for all domestic transactions (“IDR equirement”), to make itself felt.
Objectives & Agenda :
The primary objective of Insolvency and Bankruptcy Code (IBC) is the resolution of distressed assets of the insolvent debtor in a time bound structured manner and to enable such insolvent entity to continue as a going concern. IBC emerges as a fast track mechanism in completion of insolvency proceedings and aims at maximising the value of the assets of an insolvent entity. The Supreme Court judgement on Essar Steel is a landmark judgement that affirms the principles of IBC. The webinar analyses the key aspects of the judgments delivered by all the judicial forums viz. National Company Law Tribunal (NCLT), National Company Law Appellate Tribunal (NCLAT) and the Honourable Supreme Court in Essar Steel case.
This presentation discusses the question as to whether a statute on mediation is required to be enacted in India. It argues that an ADR code has to be enacted so that dispute and its resolution are seen holistically.
The document discusses the rules of statutory interpretation applied to tax statutes based on a case cited. It provides the background and context for the rules. The key rules discussed are:
1) Words are given their ordinary meaning and courts do not consider consequences of interpretation or imply meanings not clearly stated.
2) Ambiguities or doubts are resolved in favor of the taxpayer.
3) The "golden rule" allows considering consequences to avoid absurdity if the language permits.
4) The "mischief rule" allows considering reasons for legislation to advance its purpose if ambiguity exists.
More recent cases show a shift toward a more purposive approach seeking legislative intent over formalism. Courts now aim to
William Kosar What Every Budget Officer Should Know_RwandaWilliam Kosar
This document provides an overview of key contract information for budget officers. It discusses types of contracts including public contracts, general conditions of contracts, and public-private partnerships. It also covers memorandums of understanding, performance guarantees, bid rigging, and types of resource exploration contracts like production sharing agreements and power purchase agreements. Checklists are recommended to ensure all important contract details are included. The dangers of memorandums of understanding being non-binding are outlined, and performance guarantees using letters of credit or bonds are described. Finally, common forms of bid rigging like cover bidding, bid suppression, bid rotation, and market allocation are defined, along with warning signs of anti-competitive bidding practices.
Today, with us we have “Mr. Ashok Juneja” who is an Advocate and Insolvency Professional. He is Founder & Managing Partner of a multi disciplinary Law Firm “MANTRAH LAW HOUSE LLP” which is an LLP of renowned Mantrah Group)
He is also director of “MANTRAH INSOLVENCY PROFESSIONALS PVT LTD”
Mr. Juneja, aged about 63 years, is a Law Graduate, Company Secretary, Cost Accountant, M.Com. Mr. Juneja also holds Diploma in Business Finance (DBF), NSE Certification in Financial Market (NCFM) and Advance Diploma in Computer Application (ADICA) etc.
Mr Juneja, a graduate from one of the most prestigious college “Shri Ram College of Commerce” has an overall combined experience of more than 40 years in Corporate Laws including Appearances in Supreme Court, High Courts, National Company Law Tribunal (NCLT), National Company Law Appellate Tribunal (NCLAT), DRT etc.
Mr Juneja empanelled with State Bank of India and Andhra Bank as an Insolvency Professional has already handled assignments of Interim Resolution Professional (IRP), Resolution Professional (RP) and Voluntary Liquidator.
He is also member of Bar Council of Delhi, Executive Member of NCLT & NCLAT Bar Association, Bar Association of Supreme Court, Delhi High Court, Institute of Company Secretaries of India, Institute of Cost Accountant of India, CII, PHD Chamber of Commerce & Industry and ASSOCHAM.
He is also the Director on the board and Adviser to many Companies which include Public Listed Companies.
The document provides information about online training for landlords in Wales to become licensed under the Rent Smart Wales scheme. It outlines that the training is divided into 5 sections that cover topics relevant to managing rental properties legally. Learners can progress through modules at their own pace and there is a certificate awarded upon passing an assessment at the end of the course.
This document provides an overview of recent regulatory compliance updates that are relevant for insurance brokers in Australia. It discusses the key changes and requirements relating to the National Consumer Credit Protection Act 2009, compensation requirements for AFS licensees, potential refunds of stamp duty on insurance policies, disclosure of the Financial Claims Scheme, implications of double insurance provisions, proposed amendments to the Insurance Contracts Act, and new APRA data collection requirements for brokers. Compliance with the new credit licensing regime and responsible lending obligations is required if brokers provide credit assistance for premium funding.
This document discusses statutory adjudication in contracts for professional services in Hong Kong. It provides background on security of payment legislation in other countries and past surveys on payment practices. It then outlines key features of statutory adjudication, including that it provides a fast, inexpensive, and temporary binding dispute resolution process. The document discusses what types of contracts and construction activities would be covered under the proposed legislation in Hong Kong, including value thresholds. It also summarizes the adjudication procedure and rights around payment periods, suspensions for non-payment, and ineffective payment provisions.
Washington State legislative changes from 2011 (reciprocal bid preference law), 2012 (bills that passed and didn't pass), and 2013 (potential legislation affecting re-authorization of Alternative Public Works contracting.
The document summarizes the key changes made by the Building Industry Fairness (Security of Payment) and Other Legislation Amendment Act 2020 in Queensland, Australia:
1. It replaces the existing project bank account framework for Queensland government construction projects with a simplified statutory trust regime for payments to subcontractors and retention monies.
2. It increases the Queensland Building and Construction Commission's enforcement powers to monitor compliance with the new project trust requirements and introduces penalties for non-compliance.
3. For all construction contracts in Queensland, it establishes new offenses for principals and contractors who fail to pay certified or adjudicated amounts by the due date, with penalties of up to $13,345 for individuals and $66
UK Adjudicators Newsletter November 2021SeanGibbs12
The document summarizes two recent UK court cases related to construction payment adjudication.
1) In the first case, Quadro sought payment of £40k from Creagh for work under one contract. Creagh argued the adjudicator did not have jurisdiction because three separate invoices were referred, but the court found they constituted a single dispute over the total amount owed.
2) In the second case, CCCL sought £485k from Mincione following a final statement and adjudication decision. Mincione argued liquidated damages should offset this amount. The court found the adjudicator breached natural justice by not considering this defense, making the decision unenforceable.
1. The document provides a summary of recent legal cases and developments in various areas of technical claims, including costs, credit hire, causation, and liability.
2. Key cases discussed include one limiting costs in minor claims to the small claims track, another holding a credit hire company accountable for delays in authorizing vehicle repairs, and a Court of Appeal decision finding a local council did not owe visitors a duty of care at a horse fair.
3. Legislative developments covered include a bill to modernize third party rights against insurers and a proposed Consumer Insurance Bill that would update rules around misrepresentation in insurance contracts.
UK Adjudicators are an adjudicator nominating body for construction disputes and have the largest multi-disciplinary panel of adjudicators in the United Kingdom.
The document summarizes the key points from a newsletter published by UK Adjudicators in March 2020. It discusses several upcoming events related to adjudication and arbitration, including conferences in Edinburgh and London. It also summarizes a recent court case involving a dispute over whether an arbitration agreement was incorporated into a construction contract. The newsletter provides updates on adjudication schemes and conferences, and highlights an article about potential conflicts of interest for professional advisors serving as adjudicators.
February 2019 newsletter of UK Adjudicators.
MACOB 20 years on
NSW adjudication
Hong Kong adjudication
2019 Edinburgh Adjudication and Arbitration Conference
Bresco Electrical Services Ltd v Michael J Lonsdale (Electrical) Ltd [2019] EWCA Civ 27 (24 January 2019)
Chapter 21: Sales Contracts: Domestic & Global Aspects of Formation, Title, &...Tara Kissel, M.Ed
This document provides an overview of Chapter 21 from the 6th edition of the textbook "Business Law" regarding sales contracts and their domestic and international aspects. The chapter covers formation of sales contracts, title to goods, risk of loss, and the application of the United Nations Convention on Contracts for the International Sale of Goods (CISG). Key topics include the scope of Article 2 of the Uniform Commercial Code, express agreements, documentary transactions, usage of trade, gap-filling rules, identification of goods, risk of loss, and provisions of the CISG.
Time Bars and their enforceability in English law EPC contractsEversheds Sutherland
The use of time bar clauses in standard form EPC contracts is common. How effective a tool are such clauses for managing contractors’ claims for extensions of time and additional payment, and what challenges will there be in enforcing a time bar clause?
UK Adjudicators September 2019 newsletter discussing construction adjudication around the world with a look at the UK, Singapore and Australia in this edition.
UK Adjudicators are an adjudicator nominating body who nominate sole adjudicators and dispute board members in the United Kingdom and internationally. The nomination service is a free service to the parties.
The June newsletter features adjudication cases from the UK, NSW, Singapore and updates from Canada and NSW on adjudication legislation.
The document summarizes key information from the UK Adjudicators newsletter regarding security of payment reforms and developments. The newsletter discusses:
1) Hong Kong implementing a pilot program for security of payment provisions on public works contracts, including provisions for payment claims, responses, adjudication of disputes, and mandating similar provisions in subcontracts.
2) Reforms to security of payment legislation in Western Australia that will largely adopt the model used in New South Wales, introducing statutory payment timelines, requiring payment schedules to dispute payment claims, and adjudicating disputed amounts.
3) Key impacts of the changes including greater resources required to dispute payment claims through detailed payment schedules, and restrictions on raising new issues in adjudication
This document provides summaries of several articles from a law firm relating to public procurement, state aid, judicial review, and local government issues. It includes summaries of recent court cases and regulatory changes. The articles discuss the lifting of automatic suspension in public procurement cases, updates to the General Block Exemption Regulation regarding state aid, notes on procedure and interpretation in judicial review, legitimate expectations in planning contributions, LEPs (Local Enterprise Partnerships), and a new EU public procurement directive.
M32089 Construction Contracts And Dispute Resolution.docxstirlingvwriters
This document discusses construction law, contracts, and dispute resolution. It covers several topics:
- Construction disputes typically arise due to breaches of contract requirements or miscommunications between parties.
- UK legislation like the Housing Grants, Construction and Regeneration Act of 1996 and Construction Act of 1996 establish adjudication procedures for resolving disputes and regulate health and safety of construction workers.
- The Health and Safety at Work Act of 1974 and Construction (Design and Management) Regulations of 2015 aim to protect worker health and safety and manage risks during construction projects.
The Supreme Court upheld the validity of the notification bringing personal guarantors of corporate debtors under the Insolvency and Bankruptcy Code. The Court found that (1) the Code was implemented gradually based on expert recommendations to further its objectives; (2) the notification was a valid exercise of the government's powers under the Code; and (3) approval of a resolution plan for a corporate debtor does not discharge the liabilities of personal guarantors.
Construction law update august 2015 quarter 2 aColin Tomlinson
The document provides an overview of commercial management best practices for construction contracts. It discusses when commercial managers should be appointed and their key responsibilities, which include understanding contract terms, managing notification dates, and ensuring procedures are followed correctly. It then summarizes two recent court cases related to payment disputes - Caledonian Modular Ltd v Mar City Developments Ltd and Henia Investments Inc v Beck Interiors Ltd. Both cases emphasize the importance of strictly following contractual payment procedures and timelines.
Commercial and Construction Law Update Q2 2015Colin Tomlinson
The document provides an overview of commercial management best practices for construction contracts. It discusses when commercial managers should be appointed and their key responsibilities, such as managing contract terms and conditions, mapping out notification dates, and ensuring procedures are followed correctly. It also summarizes two recent court cases related to payment disputes, where the courts emphasized strict adherence to contractual payment processes and timelines.
City of London Law Society - Submittal to BEIS on Statutory Retention Deposit...Francis Ho
A supplemental submission from the City of London Law Society's Construction Law Committee sent to the Department for Business, Energy & Industrial Strategy (BEIS) on 3 December 2018 regarding potential proposals to introduce a statutory retention deposit scheme for construction contracts in the United Kingdom.
This newsletter from UK Adjudicators provides updates on security of payment laws and adjudication. It discusses training being offered in 2019 to support applicants to their adjudicator panel. It also summarizes differences between how Australian and English courts treat severing valid parts of an adjudicator's decision from parts affected by jurisdictional error. Additionally, it provides updates on legislation regarding construction retention schemes in the UK and amendments to security of payment laws in New South Wales.
HMRC revises its policy in relation to cost sharing groups following judgments from the Court of Justice. Specifically, HMRC will no longer allow the cost sharing exemption for financial and insurance businesses as the Court of Justice ruled the exemption is not available to these sectors. HMRC will provide a two month transition period for affected businesses to regularize their VAT positions. Additionally, the Court of Appeal case involves determining whether VAT on fund management services provided to the University of Cambridge's endowment fund can be attributed to the overall activities of the University.
Similar to UK Adjudicators November 2020 Newsletter (20)
UK Adjudicators are an adjudicator nominating body with the largest multi disciplinary panel in the UK.
Adjudicator nominations are made free of charge.
The newsletter provides information on recent events and updates in construction law adjudication. It summarizes that the annual London adjudication conference in August was a success, with the next major conference planned for Edinburgh in 2022. It also summarizes a recent Irish court case that enforced an adjudicator's decision and clarified that parties have an unfettered right to refer disputes to adjudication under Irish law. Upcoming events and conferences are also announced.
UK Adjudicators 2021 London Adjudication & Arbitration Conference pack with speakers slides. Speakers included:
Marion Smith QC 39 ESSEX / CIARB
Daniel Miles AQUILA FORENSICS
Abdul Jinadu KEATING CHAMBERS / UK ADJUDICATORS
Jeremy Glover FENWICK ELLIOTT
Sean Gibbs UK ADJUDICATORS / HANSCOMB INTERCONTINENTAL
Seamus O’Doherty BRG / RICS / UK ADJUDICATORS
Sean Fishlock BRG
Matt Finn ANKURA / UK ADJUDICATORS
Iain Aitchison ANKURA / UK ADJUDICATORS
Giorgiana Tecuci SCPA TECUCI PĂLTINEANU / DRBF / FIDIC
Brandon Malone SAC / RICS / CIARB / UK ADJUDICATORS
Chantelle Humphries THE BRIDGE GROUP OF ADVOCATES / UK ADJUDICATORS
Robert Sliwinski SWL CHAMBERS / UK ADJUDICATORS
Patrick Waterhouse BOWDON CONSULTING / UK ADJUDICATORS
Peter Aeberli 3PB / UK ADJUDICATORS
Karen Gough 39 ESSEX
Johan Beyers KEATING CHAMEBRS
Robert Werth WERTH CONSULTING
Dean Sayers SAYERS COMMERCIAL / UK ADJUDICATORS
Lisa Cattanach CDR / RICS / UK ADJUDICATORS
Suryen Nullamtamby BIRKETT LONG LLP / UK ADJUDICATORS
John Cock ON Q CONSULTING COLLABORATING WITH HANSCOMB INTERCONTINENTAL
Glenn Haley BRYAN CAVE LEIGHTON PAISNER LLP
Albert Yeu AECOM / UK ADJUDICATORS
Paul Checketts HANSCOMB INTERCONTINENTAL / UK ADJUDICATORS
Jonathan Pawlowski COLLYER BRISTOW
Jessica Tresham WOMBLE BOND DICKINSON
Philip Harris WRIGHT HASSALL
Justin Mort QC KEATING CHAMBERS
Giovanni Di Folco TECHNO ENGINEERING / DRBF
Adriana Spassova EQE / DRBF / FIDIC
Sharon McGahey BLACKROCK EXPERT SERVICES
Yasemin Cetinel CENTINEL LAW FIRM
Bernadette Barker BARKER CONSULTANTS
Giorgiana Tecuci SCPA TECUCI PALTINEAU
James Bridgeman SC 4-5 GRAYS INN / ARBITRATOR
Damain James DAMIAN JAMES QUANTUM & DELAY / UK ADJUDICATORS
Peter Clyde ADDLESHAW GODDARD LLP
Panel subjects and programme:
Conference 9.05am to 5.00pm (ZOOM)
09.15 to 10.30 Defining and achieving diversity in tribunals
10.30 to 10.45 break
10.45 to 12.00 Controlling costs by capping fees of tribunal members
12.00 to 12.45 Governing Law after Brexit
12.45 to 13.15 lunch
13.15 to 14.30 Statutory ADR or contractual ADR ?
14.30 to 14.45 break
14.45 to 16.00 Do experts discharge their duties to the tribunal ?
16.00 to 17.00 Management of delinquent party behaviour !
UK Adjudicators 2021 London Adjudication & Arbitration Conference has leading speakers from law firms, barristers chambers, expert firms and adjudicators and arbitrators.
UK Adjudicators London 2021 Conference
Marion Smith QC 39 ESSEX / CIARB
Daniel Miles AQUILA FORENSICS
Abdul Jinadu KEATING CHAMBERS / UK ADJUDICATORS
Jeremy Glover FENWICK ELLIOTT
Sean Gibbs UK ADJUDICATORS / HANSCOMB INTERCONTINENTAL
Seamus O’Doherty BRG / RICS / UK ADJUDICATORS
Sean Fishlock BRG
Matt Finn ANKURA / UK ADJUDICATORS
Iain Aitchison ANKURA / UK ADJUDICATORS
Murray Armes SENSE STUDIO / UK ADJUDICATORS
Giorgiana Tecuci SCPA TECUCI PĂLTINEANU / DRBF / FIDIC
Brandon Malone SAC / RICS / CIARB / UK ADJUDICATORS
Chantelle Humphries THE BRIDGE GROUP OF ADVOCATES / UK ADJUDICATORS
Robert Sliwinski SWL CHAMBERS / UK ADJUDICATORS
Patrick Waterhouse BOWDON CONSULTING / UK ADJUDICATORS
Peter Aeberli 3PB / UK ADJUDICATORS
Karen Gough 39 ESSEX
Johan Beyers KEATING CHAMEBRS
Robert Werth WERTH CONSULTING
Dean Sayers SAYERS COMMERCIAL / UK ADJUDICATORS
Lisa Cattanach CDR / RICS / UK ADJUDICATORS
Suryen Nullamtamby BIRKETT LONG LLP / UK ADJUDICATORS
John Cock ON Q CONSULTING COLLABORATING WITH HANSCOMB INTERCONTINENTAL
Glenn Haley BRYAN CAVE LEIGHTON PAISNER LLP
Albert Yeu AECOM / UK ADJUDICATORS
Paul Checketts HANSCOMB INTERCONTINENTAL / UK ADJUDICATORS
Jonathan Pawlowski COLLYER BRISTOW
Jessica Tresham WOMBLE BOND DICKINSON
Philip Harris WRIGHT HASSALL
Justin Mort QC KEATING CHAMBERS
Giovanni Di Folco TECHNO ENGINEERING / DRBF
Adriana Spassova EQE / DRBF / FIDIC
Sharon McGahey BLACKROCK EXPERT SERVICES
Yasemin Cetinel CENTINEL LAW FIRM
Bernadette Barker BARKER CONSULTANTS
Giorgiana Tecuci SCPA TECUCI PALTINEAU
James Bridgeman SC 4-5 GRAYS INN / ARBITRATOR
Damian James DAMIAN JAMES QUANTUM & DELAY / UK ADJUDICATORS
Peter Clyde ADDLESHAW GODDARD LLP
Hanscomb Intercontinental CEO Sean Gibbs spoke alongside Katie Pickering (BPE Solicitors LLP) and Keith Blizzard HCR Hewitsons) at the recent Constructing Excellence Gloucestershire Club webinar on Material Shortages and Fluctuations clauses in standard from contracts.
Contracts discussed included JCT/NEC/FIDIC & ICHEME
If you need advice do get in touch
info@hanscombintercontinental.co.uk
UK Adjudicators has the UK's largest largest multi-disciplinary panel of adjudicators and as one of the leading Adjudicator Nominating Bodies will nominate an adjudicator to resolve your dispute at cost.
UK Adjudicators London 2021 Adjudication & Arbitration Conference takes place on the 19 August as a hybrid event.
Speakers include:
Marion Smith QC 39 ESSEX / CIARB
Daniel Miles AQUILA FORENSICS
Abdul Jinadu KEATING CHAMBERS / UK ADJUDICATORS
Jeremy Glover FENWICK ELLIOTT
Sean Gibbs UK ADJUDICATORS / HANSCOMB INTERCONTINENTAL
Seamus O’Doherty BRG / RICS / UK ADJUDICATORS
Sean Fishlock BRG
Matt Finn ANKURA / UK ADJUDICATORS
Iain Aitchison ANKURA / UK ADJUDICATORS
Murray Armes SENSE STUDIO / UK ADJUDICATORS
Giorgiana Tecuci SCPA TECUCI PĂLTINEANU / DRBF / FIDIC
Brandon Malone SAC / RICS / CIARB / UK ADJUDICATORS
Chantelle Humphries THE BRIDGE GROUP OF ADVOCATES / UK ADJUDICATORS
Robert Sliwinski SWL CHAMBERS / UK ADJUDICATORS
Patrick Waterhouse BOWDON CONSULTING / UK ADJUDICATORS
Peter Aeberli 3PB / UK ADJUDICATORS
Karen Gough 39 ESSEX
Johan Beyers KEATING CHAMEBRS
Robert Werth WERTH CONSULTING
Dean Sayers SAYERS COMMERCIAL / UK ADJUDICATORS
Lisa Cattanach CDR / RICS / UK ADJUDICATORS
Suryen Nullamtamby BIRKETT LONG LLP / UK ADJUDICATORS
John Cock ON Q CONSULTING COLLABORATING WITH HANSCOMB INTERCONTINENTAL
Glenn Haley BRYAN CAVE LEIGHTON PAISNER LLP
Albert Yeu AECOM / UK ADJUDICATORS
Paul Checketts HANSCOMB INTERCONTINENTAL / UK ADJUDICATORS
Jonathan Pawlowski COLLYER BRISTOW
Jessica Tresham WOMBLE BOND DICKINSON
Philip Harris WRIGHT HASSALL
Justin Mort QC KEATING CHAMBERS
Giovanni Di Folco TECHNO ENGINEERING / DRBF
Adriana Spassova EQE / DRBF / FIDIC
Sharon McGahey BLACKROCK EXPERT SERVICES
Yasemin Cetinel CENTINEL LAW FIRM
Bernadette Barker BARKER CONSULTANTS
Giorgiana Tecuci SCPA TECUCI PALTINEAU
James Bridgeman SC 4-5 GRAYS INN / ARBITRATOR
Damain James DAMIAN JAMES QUANTUM & DELAY / UK ADJUDICATORS
Peter Clyde ADDLESHAW GODDARD LLP
The need for dispute boards on international waste to energy projects was presented to Dispute Resolution Board Foundation members and guests by Sean Gibbs of Hanscomb Intercontinental in May 2021.
The document discusses dispute resolution methods such as dispute boards, adjudication, and arbitration. It provides details on establishing a dispute board, including their composition, responsibilities, and payment structures. The text also outlines the adjudication process, including timelines for appointing an adjudicator and requiring their decision to be binding until the dispute is resolved through legal or other agreed means.
The document lists over 100 adjudicators who are members of the UK Adjudicators Panel. It provides their names and titles as "Panel Adjudicator". It also includes the website www.ukadjudicators.co.uk which offers free adjudicator nominations.
Hanscomb Intercontinental are pleased to be a supporting patron of the Vis East Moot.The programme for the week long event provides details on the competing teams, arbitrators and networking events.
Advertisements from Keating Chambers & Atkin Chambers and Hanscomb Intercontinental appear in the programme.
UK Adjudicators are an adjudicator nominating body.Nominations are free of charge and are made from our panel of adjudicators. Panel members include retired TCC judges, solicitors, barristers, surveyors, engineers, architects and other built environment professionals.
UK Adjudicators are a leading Adjudicator Nominating Body (ANB )for the construction and engineering industries.
Panel members include retired judges, solicitors, barristers, engineers, surveyors and architects.
Hanscomb Intercontinental provide expert advisory & expert witness services to the global onshore and offshore construction, engineering and shipbuilding industries.
The document lists over 100 "Adjudication Panel Members" and their titles as "Panel Adjudicator". It also includes the website www.ukadjudicators.co.uk which it states offers free adjudicator nominations. The document appears to be listing members of an adjudication panel in the UK and contact information for the organization.
UK Adjudicators can nominate UK Adjudicator panel members to resolve your disputes. There is no fee charged to make the nomination. Members comprise comprising solicitors, barristers, surveyors, architects, engineers and other specialist built environment professionals.
The document lists over 100 individuals identified as members of the UK Adjudicators Panel. It provides their name and title ("Panel Adjudicator") and links to the website www.ukadjudicators.co.uk, which offers free adjudicator nominations. The repeated structure suggests this is a comprehensive listing of adjudicators available through this organization in the UK.
The document discusses two recent UK legal cases related to construction adjudication and expert witnesses. In the first case, the TCC refused to grant an injunction to stop an adjudication from proceeding due to challenges presented by the coronavirus pandemic. In the second case, the TCC ruled that an expert witness firm owed a fiduciary duty of loyalty to a client, preventing it from taking expert roles adverse to that client on related matters. This second ruling could significantly impact expert witness firms by restricting their ability to take new expert assignments.
More from Sean Gibbs DipArb, FCIARB, FCIOB, FRICS, MICE (20)
The subject matter of this study is the legislation and practice of disciplinary liability for corruption and corruption-related offenses in Ukraine and, in a comparative aspect, abroad.
The purpose of the study is to identify gaps, contradictions and other shortcomings in the legislative regulation and practice of disciplinary liability for corruption and corruption-related offenses and, on this basis, taking into account positive foreign experience, to propose appropriate amendments to Ukrainian legislation.
This documents talks about RERA Execution Panchkula Authority Powers wherein it has been delegated to AO (Adjudicating Officer) to hear execution petitions.
The Real Estate (Regulation and Development) Act, 2016
Chapter-X Miscellaneous
Section 81: Delegation.
81. The Authority may, by general or special order in writing, delegate to any member, officer of the Authority or any other person subject to such conditions, if any, as may be specified in the order, such of its powers and functions under this Act (except the power to make regulations under section 85, as it may deem necessary.
HARMONIOUS CONSTRUCTION RULE by Puja Dwivedilegalpuja22
INTRODUCTION TO HARMONIOUS CONSTRUCTION RULE:-
Harmonious construction is a principle of statutory interpretation aimed at reconciling conflicting provisions within a legal framework.
It involves interpreting statutes in a manner that avoids inconsistencies and gives effect to the overall legislative intent.
This rule is pivotal in resolving legal disputes where different laws or constitutional provisions appear to conflict.
PRINCIPLES OF HARMONIOUS CONSTRUCTION RULE:-
Interpret statutes to avoid conflicts and give effect to legislative intent.
Maintain consistency within legal frameworks.
Balance conflicting provisions while upholding constitutional values.
ROLE OF JUDICIARY IN HARMONIOUS CONSTRUCTION:-
Judiciary acts as a mediator in resolving legal conflicts.
Courts ensure harmonious interpretation of laws to uphold justice.
Judicial decisions establish precedents for future legal disputes.
CASE LAWS :-
Venkataramana Devaru v. State of Mysore (1957)
Citation:
Venkataramana Devaru v. State of Mysore, 1957 (AIR 1958 Mys 38)
Fact:
Trustees of Sri Venkataramana Temple filed a suit under Section 92 of CPC regarding the exclusion of Harijans from the temple after the enactment of the Madras Temple Entry Authorization Act (Madras V of 1947).
The temple trustees claimed that the temple was private and exclusively meant for Gowda Saraswath Brahmins, hence exempt from the Madras Act.
Issue:
Whether the Madras Temple Entry Authorization Act applied to Sri Venkataramana Temple despite the trustees' claim of its private nature.
Whether Section 3 of the Madras Act violated Article 26(b) of the Indian Constitution, which protects the rights of religious denominations.
Judgment:
The High Court of Madras ruled that while the public could worship in the temple, the trustees had the right to exclude the general public during certain ceremonies reserved for Gowda Saraswath Brahmins.
The Supreme Court clarified that the Madras Act applied to Sri Venkataramana Temple and harmonized Articles 25(2)(b) and 26(b) of the Constitution to uphold the Act's validity, ensuring access to the temple for all classes of Hindus.
K.M. Nanavati v. State of Maharashtra (1961)
Citation:
K.M. Nanavati v. The State of Maharashtra, 1961 (AIR 1962 SC 605)
Fact:
Naval Commander K.M. Nanavati was accused of murdering his wife's secret lover, Prem Ahuja.
Nanavati was tried under IPC Sections 302 and 304, and a special jury acquitted him.
Issue:
Whether the decision of the special jury acquitting Nanavati was logical given the evidence of the case.
Whether the suspension order by the Governor under Article 161 of the Constitution could be applied while the case was sub-judice.
Judgment:
The High Court of Bombay overturned the jury's decision, holding Nanavati guilty of murder based on the circumstances of the case.
The Supreme Court ruled that Article 161's suspension power couldn't be exercised while the case was pending before the judiciary, emphasizing the importance of harm
A petition for justice. The witness provided false delusional testimony. The court made several errors which include denying witness to testify. The abuser has relationship with the court. The victim is disabled and can't defend herself due to communication disability.
Fordham University transcript.Buy fake diplomaCollege diploma
WhatsApp: +852 56142185
Create a fake Fordham University transcript. Buy a fake Fordham University diploma. Buy a fake Fordham University degree. Fake Fordham University diploma for sale.
Skype: adolph.863
QQ/WeChat: 648998850
Email: buydocument1@gmail.com
https://www.buydocument.net
https://www.buyfastdegree.com
https://www.getadiploma9.com
https://www.diploma999.com
The Law of Dogs in Sectional Title SchemesAshwini Singh
The Law of Dogs in Sectional Title Schemes (in South Africa):
-PCR 1(1) of the STSM Regulations:
“The owner or occupier of a section must not, without the trustees’ written consent, which must not be unreasonably withheld, keep an animal, reptile or bird in a section or on the common property.”
-PCR 1(2) of the STSM Regulations:
“An owner or occupier suffering from a disability and who reasonably requires a guide, hearing or assistance dog must be considered to have the trustees’ consent to keep that animal in a section and to accompany it on the common property.”
-Subsection 39(2)(c) of the CSOS Act:
“An order declaring that an animal is being kept in a community scheme contrary to the scheme governance documentation, and requiring the owner or occupier in charge of the animal to remove it…"
-The Trustees of The Ridge Body Corporate v Wijne:
Adjudication Order Paragraph 47:
“The continued conduct [of the Respondents] to keep pets in their unit without authorisation of the Trustees of the Ridge is contrary to the provisions of the scheme’s conduct rules [and] is a violation of the rules and amounts to usurping the authority of the Trustees if not disregarding it…”
Adjudication Order Paragraph 50:
“In terms of the scheme rules, it is not permissible for an owner or occupier of a unit to keep an animal or pet without prior authorisation of the trustees. In the premises, [the Respondents] are found to have acted in contravention of the scheme rules of The Ridge and have acted contrary to the provisions of Section 39(2)(b) of the Community Schemes Ombud Service Act…”
Adjudication Order Paragraph 53.1:
“The Respondent … is ordered to remove the pet dog and parrot kept in … The Ridge and out of the scheme within 30 days of delivery of this order.”
Know what is Proforma B in Panchkula RERA Complaint Authority when you are mentioning the respondents. The Authority after consideration resolved that for all intents and purposes, the respondents whose name/ address/ other details, are stated in Proforma-B shall be treated as respondent(s) and the respondent whose name are not mentioned in Proforma-B shall not be considered as respondents to the complaint.
An example of a petition written pro-se by the victim to defend against delusional false accusation by an abuser.
Writ of Certiorari written by an autistic defendant who is a victim of harassment and was falsely accused by her very own abuser.
Individuals with autism has difficulties in communicating, and this gives plenty of advantages for abusers because autistic individuals are naive and not able to defend themselves due to communication issues. The abuser in this case happens to be a school principal who bullies and harasses disabled students and parents on regular basis, but she is able to walk away free because of her craftiness and her exceptional abilities to lie. She is a pathological liar and she is able to deceive law enforcement and the court. This document describes the truth and the ordeal that one of her victims had to go through without being able to get help because the abuser was able to manipulate a large number of people. This document also shows how the current justice system fails to accommodate disabilities especially autism spectrum disorders. Despite a campaign by Pennsylvania Supreme Court to enable autistic individuals to access justice, the courts in Pennsylvania, including the Supreme Court itself is still far far away from understanding Autism. Autistic people have to suffer in silence, and many of them are victims of abuse but they are not able to defend themselves. This explains why suicide rates amongst autistic populations are extremely high.
1. WWW.UKADJUDICATORS.CO.UK
NOVEMBER 2020 NEWSLETTER
1 | P a g e
EDITORS COMMENTS
The UK is now in a second lockdown and the
likely impact on the construction industry and
society moving forward is not known. Like
most other organisations we place safety of
others in society before our own needs and
wants and we have adjusted our first major
planned conference for 2021.
The annual Edinburgh Adjudication and
Arbitration conference will therefore be
taking place as a virtual event during the week
ending 5th
March 2021. As in previous years
this will precede the Edinburgh University Pre
Vis Moot.
Two cases that show that adjudication is
useful to a Party in liquidation and that in
such circumstances the courts will enforce an
adjudicator’s decision (Balfour Beatty Civil
Engineering Ltd & Anor v Astec Projects Ltd
[2020] EWHC 796 (TCC) and Styles and Wood
v GECIF Trustees Unreported 4 September
2020) should lead to more parties and in
particular their liquidators and administrators
referring disputes to adjudication.
At the Adjudication Society Virtual Conference
Janey Milligan provided an update on the
annual adjudication report and also feedback
from the main Adjudicator Nominating Bodies
indicating that there is a current trend of the
number of disputes increasing though it is not
possible from Janey’s information to reach a
conclusion if this is as a result of COVID-19,
economic pressure, ability of liquidators to
refer matters to adjudication or a very
probable combination of all of these.
We have a range of articles on adjudication
from across the globe and further Canadian
recognition of the benefits of adjudication to
resolve payment disputes in construction.
Alberta has seen the benefits of legislating for
adjudication and prompt payment in the
construction industry and is currently passing
legislation through its Parliament which is
likely to be up and running in 2021.
Sean Gibbs LLB(Hons) LLM MICE FCIOB FRICS
FCIARB, is a director with Hanscomb
Intercontinental and is available to serve as an
arbitrator, adjudicator, mediator, quantum
expert and dispute board member.
sean.gibbs@hanscombintercontinental.co.uk
2. WWW.UKADJUDICATORS.CO.UK
NOVEMBER 2020 NEWSLETTER
2 | P a g e
RECOVERY OF PARTY COSTS IN
ADJUDICATION
The position regarding the award of party
costs in adjudication proceedings is one which
has been revised, bit by bit, over the years.
The high water mark was Bridgeway v Tolenti
in 2000, which permitted clauses that would
oblige a referring party to make payment of
all of the adjudicator and responding party’s
costs regardless of outcome.
Yuanda v WW Gearii
in 2010 sought to put an
end to such practices (in England and Wales at
least), treating practical or commercial
restrictions on the ability to adjudicate at any
time as seriously as contractual restrictions.
The Local Democracy Economic Development
and Construction Act 2009 (“the LDEDCA”)
took aim at the same targets and introduced,
from 2011, an express prohibition on any
clauses which removed the discretion of
adjudicator to apportion their fees as they
saw fit. Whilst parties were free to agree that
an adjudicator could award party costs in the
proceedings, such an agreement would have
to be recorded in writing and be made after
the service of a notice of adjudication.
For a while, the issue of adjudicators awarding
party costs was no longer a consideration.
Things seemingly changed with new
regulations introduced in 2013 which
amended The Late Payment of Commercial
Debts (Interest) Act 1998 (“the Late Payment
Act”).
Statutory Interest
The Late Payment Act introduced a statutory
right to claim interest on late payments where
there was no adequate contractual remedy
for interest due on late payments.
Over the years, the provisions of the Late
Payment Act have been updated and
amended by various sets of regulations. In
2002, for example, Section 5A was added to
the Act which provided for a fixed sum to be
added to the time related interest due, on a
sliding scale from £40 for debts of less than
£1,000 to £100 for debts of over £10,000.
It’s probably fair to say that this additional
compensation was relatively uncontroversial.
Claims in adjudication which added these
modest lump sums to statutory interest were
often granted by adjudicators.
This additional lump sum started to demand
rather more attention after the introduction
of the Late Payment of Commercial Debts
Regulations 2013 (“the 2013 Regulations”) in
which Section 5A of the Late Payment Act was
amended, as follows:
“(2) After subsection (2) insert—
(2A) If the reasonable costs of the supplier in
recovering the debt are not met by the fixed
3. WWW.UKADJUDICATORS.CO.UK
NOVEMBER 2020 NEWSLETTER
3 | P a g e
sum, the supplier shall also be entitled to a
sum equivalent to the difference between the
fixed sum and those costs.”
On the face of it, the door was now opened
for claiming party costs in adjudication, albeit
only in the limited circumstances where the
statutory late payment provisions applied.
The View of the Courts
It wasn’t long before the courts were asked to
consider this apparent exception to the
general rule that party costs were not
recoverable without the agreement of both
parties, post-notice of adjudication.
The decision in Lulu v Mulalleyiii
gave some
encouragement, finding that an adjudicator’s
decision which included party costs in this
way was enforceable. The challenge in that
case appears to have been very narrowly
argued though. Rather than attacking the
award as being contrary to the requirements
of the Construction Act,iv
it was argued that
the adjudicator lacked jurisdiction to reach
such a decision. The interest was awarded in
respect of a counterclaim raised by the
responding party within the proceedings. It
was unsuccessfully argued that the award of
those costs was beyond the scope of the
dispute which had been referred.
It was held that the decision in Allied v
Paradigmv
was relevant and a responding
party could “raise any defence to the claim
when it’s referred to adjudication”. Any
counterclaim could be considered so long as it
was consequential upon or connected to the
referred dispute.
In Lulu, it was decided that the costs of
running the adjudication were ancillary or
connected to the dispute described by the
notice of adjudication and the adjudicator
therefore had the jurisdiction to consider
them. The adjudicator’s decision was
enforced.
Shortly afterwards, however, the judgment in
Enviroflow v Redhillvi
brought a swift end to
claims of this type within adjudication.
Here, the Court weighed up two competing
statutory provisions. On the one hand, section
5A of the Late Payment Act said that if the
fixed lump of £40 to £100 added to the
interest was not sufficient to cover the party’s
reasonable costs of pursuing the debt, then an
amount equal to those costs should be added
to the interest instead.
On the other hand, section 108(A) of the
Construction Act said that any provision of a
contract which sought to allow an adjudicator
to allocate party costs would be ineffective
unless made in writing after the service of the
notice of adjudication.
It was held that the requirement of section 5A
of the Late Payment Act was to be implied
into a commercial contract where there was
4. WWW.UKADJUDICATORS.CO.UK
NOVEMBER 2020 NEWSLETTER
4 | P a g e
no contractual mechanism for dealing with
late payments. However, once implied it
would immediately be rendered ineffective by
section 108(A) of the Construction Act. The
Construction Act prevented the implication of
a right to claim debt recovery costs within
adjudication.
This point is now settled and attempts to
claim party costs via the Late Payment Act are
likely to be given short shrift. However, whilst
that may be the case, is this a desirable
outcome? Is there a way of reconciling the
two apparently contradictory statutory
provisions? Does Enviroflow limit access to
adjudication for those most in need of the
process and who is being protected by the
Enviroflow prohibition on claiming party
costs? Given the recent advent of the Low
Value Dispute adjudication schemes, is it not
perhaps time to consider whether the full set
of rights granted by the Late Payment Act
should be extended to the construction
industry.
Implementing EU Directives and the 2013
Regulations
The Late Payment Act’s 2013 Regulations
were introduced in order to implement an EU
Directive.vii
Directives do not have automatic
legal effect within the EU Member States.
Instead, they set minimum standards which
each member is then required to incorporate
into their own national law.
Article 2 of the Directive stated that:
“This Directive shall apply to all payments
made as remuneration for commercial
transactions”
Article 3 of the Directive stated that:
“Member States may exclude debts that are
subject to insolvency proceedings instituted
against the debtor, including proceedings
aimed at debt restructuring”
The scope of the Directive was clear. It was to
apply to all commercial transactions. Whilst
exclusions could be made in cases of
insolvency, there was nothing which
permitted specific industries to be exempt.
Article 6 of the Directive stated that:
“1. Member States shall ensure that, where
interest for late payment becomes payable in
commercial transactions in accordance with
Article 3 or 4, the creditor is entitled to obtain
from the debtor, as a minimum, a fixed sum of
EUR 40.
2. Member States shall ensure that the fixed
sum referred to in paragraph 1 is payable
without the necessity of a reminder and as
compensation for the creditor’s own recovery
costs.
3. The creditor shall, in addition to the fixed
sum referred to in paragraph 1, be entitled to
obtain reasonable compensation from the
5. WWW.UKADJUDICATORS.CO.UK
NOVEMBER 2020 NEWSLETTER
5 | P a g e
debtor for any recovery costs exceeding that
fixed sum and incurred due to the debtor’s
late payment. This could include expenses
incurred, inter alia, in instructing a lawyer or
employing a debt collection agency”
[emphasis added]
The small lump sum, already provided for by
the Late Payment Act’s 2002 Regulations, is
referred to. In addition, there is the
entitlement to claim the costs of recovering a
late payment. Not only that, but the scope of
those costs expressly included appointing a
lawyer or a debt collection agency.
The Directive therefore required that a
statutory mechanism be introduced whereby
a claimant relying on late payment regulations
was entitled to claim its debt recovery costs
(which could include legal fees). All
commercial transactions were to be covered
by these new rules. No exceptions could be
made for any specific classes of contract. The
2013 Regulations were the method by which
those mandatory requirements would be
incorporated into English and Welsh law.
The EU Commission monitors the proposed
implementation of directives into local law,
ensuring compliance with the relevant
requirements. In this case, there was nothing
to suggest that the 2013 Regulations weren’t
going to successfully implement the Directive.
The barrier to implementation of all of the
requirements arises not from the 2013
Regulations, but from the existing
Construction Act.
Did Parliament intend that the 2013
Regulations (or that part which relates to the
recovery of costs) should not apply to
construction contracts and the adjudication
process? It seems unlikely, since any attempt
to limit the scope of the 2013 Regulations
would surely have seen the EU Commission
reject the proposed regulations.
It is obviously a little late now for us to ask or
expect the EU Commission to ride to the
Directive’s rescue and insist that Parliament
adjusts local law to fully implement its
requirements.
Balancing Acts
Notwithstanding the decision in Enviroflow,
can we perhaps pick a way through the
competing legislation to allow a party relying
on the Late Payment Act to recover costs in
adjudication, whilst still maintaining the
Construction Act’s section 108(A) prohibition
on awarding party costs without an express
post notice of adjudication agreement?
Section 1(1) of the Late Payment Act states:
“It is an implied term in a contract to which
this Act applies that any qualifying debt
created by the contract carries simple interest
subject to and in accordance with this Part.”
6. WWW.UKADJUDICATORS.CO.UK
NOVEMBER 2020 NEWSLETTER
6 | P a g e
The entitlement to claim the recovery costs of
pursuing a debt arises under section 5A(2A) of
the Late Payment Act. Section 5A(3) then
states that:
“The obligation to pay a sum under this
section in respect of a qualifying debt shall be
treated as part of the term implied by section
1(1) in the contract creating the debt.”
Section 1(1) provides for an implied term
which allows interest to be claimed. Section
5A(3) then says that the costs of recovering
the debt are also granted under section 1(1).
So, what is being awarded here? Is it a party’s
costs of fighting an adjudication to recover a
late payment? Or is it interest which includes
an amount equal to the party’s costs? If we
view it as the latter, then we find a solution to
the problem.
It is not controversial that an adjudicator is
entitled to award interest as a part of their
decisions. Section 20(c) of the Scheme says
that the adjudicator may “having regard to
any term of the contract relating to the
payment of interest decide the circumstances
in which, and the rates at which, and the
periods for which simple or compound rates of
interest shall be paid”.
If we say that we are awarding a lump sum as
interest which happens to equal the party
incurred costs of conducting the adjudication,
do we manage to avoid the prohibition at
section 108(A) of the Construction Act? After
all, the adjudicator would, strictly speaking,
not be awarding costs themselves, but an
amount of interest to the same value.
In that way, do we obey the apparently
competing requirements of two different
Acts? We don’t create an exception to the
Directive which was never intended and we
also ensure that all commercial transactions
attract the rights stated within the Directive.
At the same time, we don’t open the
floodgates to contract clauses which seek to
deter adjudication by giving adjudicators a
general ability to award party costs. The
award of party costs as interest is limited to
circumstances where the Late Payment Act
applies and a separate agreement after the
service of the notice of adjudication is still
required in other circumstances.
Conclusions
If we consider that there is a way, albeit in
limited circumstances, whereby adjudicators
could award party costs, we should perhaps
also consider whether or not they should.
If a party, when negotiating its contracts,
decides that it does not want to be at risk of
paying the other party’s costs for any future
adjudication proceedings, then the solution is
simple. It includes an express provision in its
contracts for interest in the case that it is late
in making payments due.
7. WWW.UKADJUDICATORS.CO.UK
NOVEMBER 2020 NEWSLETTER
7 | P a g e
Even without pre-agreed interest rates, a
paying party can avoid the risk of paying the
other party’s costs by complying with the
Construction Act and issuing payment and/or
pay less notices in a timely manner.
That is all that is required: obey good practice
in drafting a commercial contract and don’t
allow the Late Payment Act to step in and fill
in the gaps, and then also obey good practice
when it comes to certifying payments.
Put that way, we can see who it is that
benefits from the position as it stands post
Enviroflow. The beneficiaries are those parties
who employ others to carry out construction
works without including express provisions for
interest on late payment and without issuing
either timely payment or pay less notices. Are
these the parties we want to protect? Are
these the parties we are prepared to make an
exception to the Late Payment Act for?
There appears to be a consensus that the
adjudication process has become more
complex and expensive than originally
intended, with those at the lower end of the
market being priced out of using it as an
effective means of dispute resolution.
The Low Value Dispute adjudication schemes
recently introduced are an attempt to address
the problem. However, the limit on the length
of submissions and evidence (which, at one
lever arch file, can still be substantial) and a
limit on the amount which an adjudicator can
charge seems scant consolation for a small
subcontractor who has made an application
for payment, received no payment or pay less
notice and is then faced with a contractor
who simply refuses to pay. In circumstances
such as those, shouldn’t our sympathy be with
the injured party? Shouldn’t we refocus our
view of the competing legislation, remind
ourselves why it was introduced and ensure it
works to the benefit of those most in need of
the intended protections?
Adjudication was introduced to maintain
cashflow within the construction industry.
The Late Payment Act was intended to give a
remedy to those being denied sums which
were indisputably due.
The LDEDCA amendments to the Construction
Act were instigated to strengthen the payee’s
position by making sums applied for become
due automatically if the payer ignored them.
Finally, the Directive and 2013 Regulations
expressly set out to ensure that a party to a
commercial transaction would be entitled to
recoup the costs of recovering a late debt.
All that legislation points one way, but the
current interpretation has removed the
intended benefit to those denied their money
in the industry; an industry that was so bad at
maintaining cashflow it required additional
8. WWW.UKADJUDICATORS.CO.UK
NOVEMBER 2020 NEWSLETTER
8 | P a g e
statutory rules to be imposed on it via the
Construction Act.
I would argue that we should consider who
this legislation was all intended to protect.
Where we find that those most in need of this
protection have fallen through the gaps, we
should plug the gaps and give them back the
rights which Parliament and the EU
considered they should have.
i
Bridgeway Construction Ltd v Tolent Construction
Ltd (2000) CILL 1662
ii1
Yuanda (UK) Co Ltd v WW Gear Construction Ltd
[2010] EWHC 720
iii1
Lulu Construction Ltd v Mulalley & Co Ltd.
[2016] EWHC 1852
iv
Housing Grants, Construction and Regeneration
Act 1996
v
Allied P&L Ltd v Paradigm Housing Group Ltd
[2009] EWHC 2890
vi
Enviroflow Management Ltd v Redhill Works
(Nottingham) Ltd (2017) [unreported]
vii1
EU Directive 2011/7/EU
Tony Clough – Director - Base Quantum Ltd.
Base Studios, Aldwych House, London, WC2B
4HN
T: +44 207 043 0993 / M: +44 7854 489591
tony.clough@base-quantum.co.uk
ADVERSE INFERENCES AND
ADJUDICATION – VICTORIA
The recent Victorian Court of Appeal decision
in 1155 Nepean Highway Pty Ltd v Promax
Buildings Pty Ltd [2020] VSCA 253 examines
the inferences that an adjudicator can draw
from the absence of supporting material
provided by the respondent to a payment
claim.
In 5MF58, we covered the Trial Division
proceedings. On appeal, the applicant (1155
Nepean Hwy) argued that the trial judge had
erroneously approved the approach of the
adjudicator. At issue – the ability to draw
adverse inferences from the applicant's failure
to adduce contradictory material in the
adjudication, even though the statutory
prohibition in the Building and Construction
Industry Security of Payment Act 2002 (Vic)
(SOP Act) prevented the applicant from
lodging an adjudication response.
The Court agreed. "The applicant's silence in
the adjudication could not be taken as
indicating anything at all about the strength of
its case" in the circumstances. Here, the fact
that the applicant had not provided a
payment schedule meant that section 21(2A)
9. WWW.UKADJUDICATORS.CO.UK
NOVEMBER 2020 NEWSLETTER
9 | P a g e
of the SOP Act prevented the applicant from
lodging an adjudication response. Also, the
adjudicator had not sought further
submissions or material under section 22(5).
Relevantly, however, the Court went on to
distinguish between an adverse inference
based on the absence of an adjudication
response and the applicant's earlier failure to
serve a payment schedule.
To the latter, the Court reasoned that:
"…an inference drawn, not from the absence
of an adjudication response but from the
applicant’s failure to provide a payment
schedule, is in a different position… A
recipient of a payment claim may be taken to
know of the critical significance of a payment
schedule to the operation of the Act in
general and to the making of an adjudication
determination in particular. … As a matter of
common sense, a recipient of a payment
claim who does not respond to it might
rationally be thought to have no basis upon
which to contest it."
On that basis, the Court held that it was
"permissible for an adjudicator to infer, based
on the failure of a recipient of a payment
claim to provide a payment schedule, that the
recipient was not in a position to contest the
claim".
In the end, the Court declined to find that the
adjudicator drew the inference identified by
the applicant.
The applicant also argued that the contract
drawings constituted part of the "construction
contract" which was required to be
considered by the adjudicator pursuant to
section 23(2)(b) of the SOP Act, so that a
failure to have regard to them rendered the
determination void under section 23(2B).
Although not forming a separate ground of
appeal, the Court considered this argument
and made observations regarding what
constitutes "the provisions of the construction
contract from which the application arose" for
the purposes of section 23(2)(b). The Court
observed:
"…two interpretations are open. On the
broader view, all the contents of documents
having force as part of the contract or
arrangement constituting the construction
contract make up the provisions of that
contract. On a narrower reading, the
provisions of a construction contract are to be
found only in the contract executed by the
parties, and not in other documents
incorporated by reference in that document."
Ultimately the Court concluded that the text
of section 23(2)(b) supports the narrower
approach, noting (among other things) that
the use of the expression "the provisions of
the construction contract", rather than "the
10. WWW.UKADJUDICATORS.CO.UK
NOVEMBER 2020 NEWSLETTER
10 | P a g e
construction contract" in
section 23(2)(b) suggests that the section
"contemplates something other than the
whole of the construction contract as broadly
defined". In reaching this conclusion, the
Court also adopted a practical approach
consistent with the expeditious conduct of
adjudications. The Court determined that
section 23(2)(b) sets a basal level of
contractual material that an adjudicator must
always consider, while empowering the
adjudicator to demand further submissions,
including the provision of documents, where
the adjudicator considers that the parties
have not provided all "relevant
documentation".
PARTNER , BRISBANE, SYDNEY
T +61 7 3292 7025 | +61 2 9353 4130
scapelli@claytonutz.com
SOP REMINDER: PURCHASE
ORDERS AND THE RISK OF
MULTIPLE CONSTRUCTION
CONTRACTS
The recent NSW Supreme Court decision in
Acciona Infrastructure Australia Pty Ltd v
Holcim (Australia) Pty Ltd [2020] NSWSC 1330,
highlights the issue of purchase orders
resulting in multiple construction contracts –
rather than one construction contract.
The plaintiff (Acciona) entered into an
Agreement with the defendant (Holcim) for
the supply of concrete. On 28 May 2020,
Holcim served a payment claim on Acciona for
concrete allegedly supplied. On 12 June 2020,
Acciona responded with a nil payment
schedule. Holcim submitted an adjudication
application for the claim, and an adjudication
determination was made in favour of Holcim
for $2.9 million. Acciona challenged the
adjudication determination.
Acciona argued that the adjudicator lacked
jurisdiction because there was neither a valid
payment claim nor a valid adjudication
application because the payment claim
contained claims for work done under two or
more contracts. Section 13(5) of the Building
11. WWW.UKADJUDICATORS.CO.UK
NOVEMBER 2020 NEWSLETTER
11 | P a g e
and Construction Industry Security of
Payment Act 1999 (NSW) (SOP Act) specifies
that a claimant can only serve one payment
claim in any particular month for any work
done or goods and services supplied in that
month. Justice Hammerschlag referred to the
judgment of Trinco (NSW) Pty Ltd v Alpha A
Group Pty Ltd [2018] NSWSC where the Court
held that a single progress claim cannot
validly claim for work done under more than
one contract. Relevantly, under clause 2(c) of
the Agreement, the issue of a purchase order
resulted in a separate contract coming into
existence between the parties. Applying
Trinco, Justice Hammerschlag concluded that
the payment claim straddled numerous
purchase orders and therefore did not
constitute a valid payment claim because
each purchase order was a separate contract.
As a result, the adjudicator had no jurisdiction
because the payment claim was invalid as per
section 13(5) and was therefore ineffective to
engage the operation of the SOP Act.
Justice Hammerschlag also rejected a
procedural fairness argument advanced by
Acciona that turned on its facts.
This case highlights the importance of reading
the provisions of the SOP Act within the
context of the agreement between the
parties. In this case, the fact that each
purchase order resulted in the creation of a
new contract meant that Holcim needed to
prepare a separate payment claim and
adjudication application for each purchase
order in order for the payment claim to be
valid and for the adjudicator to have
jurisdiction in relation to the dispute.
Frazer Moss
Clayton Utz
PARTNER , BRISBANE
T +61 7 3292 7204
fmoss@claytonutz.com
12. WWW.UKADJUDICATORS.CO.UK
NOVEMBER 2020 NEWSLETTER
12 | P a g e
JRT DEVELOPMENTS LTD V TW
DIXON (DEVELOPMENTS) LTD:
WHEN ENFORCEMENT IS
`MANIFESTLY UNJUST'
In the recent case of JRT Developments Ltd
(JRT) v TW Dixon (Developments) Ltd (TWD)
[2020] the TCC has shown that parties seeking
to enforce "smash and grab" adjudication
awards will not be able to do so in
circumstances where it would be manifestly
unfair.
Background
Of interest and significance in this case is the
fact that the parties in dispute are related. JRT
is owned and controlled by Mr Jonathan
Woodcock, the nephew of the sole
shareholders and directors of TWD, Mr and
Mrs Dixon. Mr and Mrs Dixon set up TWD,
with Mr Woodcock's assistance, solely for the
purposes of developing 14 new homes on
farmland near Market Drayton in Shropshire.
They are elderly and have no prior
involvement in the construction industry.
JRT and TWD entered into a JCT Minor Works
Contract with Design 2011 Edition ("the JCT
Contract") and a socalled `Commercial
Agreement' ("the Commercial Agreement"),
both dated 22 June 2016, for the design and
construction of the new homes.
The Commercial Agreement confirmed that
JRT was to manage the project and provided
that:
"The development will be constructed on a
cost plus basis covered through funding of
means (sic) of the Communities and Housing
Association. The associated costs and
overheads of TW Dixon will be covered by JRT
Developments".
"The Properties will be delivered at cost plus
the business overheads of JRT. Agreement of
profit share...is to be split against a 50:50
ratio of gross profit minus the plot value and
the associated build and sale costs"
Clearly, the relationship between the parties
was unusual; the dealings between them
were very informal so as to be more like that
of joint venture partners than that of
employer and contractor in an arm's length
construction contract. Mr Woodcock even
arranged the funding for the project (a loan
from the Homes and Communities Agency
(HCA)).
Throughout the duration of the project JRT
made no direct requests for payment from
TWD; rather JRT liaised direct with HCA as
funder, who made regular payments to TWD
based on periodic valuations of the work. JRT
issued invoices to TWA for amounts approved
13. WWW.UKADJUDICATORS.CO.UK
NOVEMBER 2020 NEWSLETTER
13 | P a g e
by HCA, which were then paid using the
funding provided.
The dispute
The relationship between the parties
gradually deteriorated due to cost overruns
and delays, as well as alleged actions on the
part of JRT. The JCT Contract was eventually
terminated by JRT on 13 June 2019. The
parties then engaged in informal dialogue as
regards the resolution of outstanding
payments, said to be in the sum of
952,578.97. This dialogue continued until JRT
issued a Disputed Payment Notice under the
terms of the JCT Contract, on 19 September
2019. It is evident that TWD failed to
understand the significance of the Disputed
Payment Notice and did not serve a pay less
notice as required.
On 14 November 2019, the first day on which
it was able to do so, JRT referred the dispute
to Adjudication. The adjudicator decided in
favour of JRT, concluding that the Disputed
Payment Notice was valid and that TWD must
pay as a result of having failed to serve a pay
less notice. JRT issued proceedings and sought
summary judgment to enforce the decision.
TWD subsequently brought a claim under Part
7 seeking a stay of enforcement on basis of
`special circumstances', being:
a) The probable inability of JRT to repay the
judgment sum at the end of the substantive
trial - Wimbledon Construction Company 200
Ltd v Vago [2005]1; and
b) the risk of manifest injustice if no stay was
granted, as a result of TWD's inability to pay
and all the circumstances of the case -
Hillview Industrial Development (UK) Ltd v
Botes Building Ltd [2006]2) and Galliford Try
Building Ltd v Estura [2015]3
The TCC
Inability to repay the judgment sum
Wimbledon Construction v Vago
To meet the test set out in the Wimbledon
case, TWD needed to show:
1. The probable inability of JRT to repay the
judgment sum at the end of the trial in TWD's
claim.
2. That JRT's financial position was not the
same or similar to its financial position at the
time the JCT Contract was entered into (22
June 2016).
3. That JRT's financial position was not due
either wholly or in significant part due to
TWD's failure to pay the sums awarded in the
adjudication.
HHJ Watson found that, whilst JRT was not
technically insolvent, it was "highly probable"
that JRT would be unable to repay the
judgment sum, thus satisfying the first limb of
the Wimbledon test. She also concluded that,
14. WWW.UKADJUDICATORS.CO.UK
NOVEMBER 2020 NEWSLETTER
14 | P a g e
having reviewed JRT's changing financial
position during the relevant period, and
taking onto account factors such as JRT's
significant loans, the management of its
finances, arrangements with creditors and
lack of profit, the financial position of JRT was
indeed substantially worse than when the JCT
Contract was entered into. As such, JRT posed
a significantly higher financial risk than it did
in 2016, thus satisfying the second limb of the
test. Finally, HHJ Watson found that JRT's
financial position was not caused either
wholly or in significant part by TWD's failure
to pay the sums awarded by the adjudicator.
TWD therefore successfully demonstrated all
three limbs of the Wimbledon test.
Manifest Injustice
The principle of staying adjudication
enforcement in situations of manifest
injustice was first established in the case of
Galliford Try Building Ltd v Estura Ltd. Estura
had failed to serve a pay less notice, leading
to an award in Galliford Try's favour. Estura
would have been unable to pay the award in
full pending a final valuation of the works,
hence the court deeming this unfair and
granting a partial stay in execution.
In the similar circumstances of the current
case, the TCC found that TWD would not be
able to pay any part of the judgment sum
without rendering itself immediately insolvent
and being forced into liquidation. HHJ Watson
noted:
The highly unusual project funding
arrangements, whereby the relationship
between the parties was not that of employer
and contractor at arm's length.
During the entire three-year course of the
contract, JRT limited its claims for payment to
the sums recovered from HCA. The payment
terms of the JCT Contract were ignored by
both parties. It was only after termination
that JRT sought to rely on the contractual
payment provisions, clearly intending to
trigger a referral to adjudication and an award
of the full sum claimed. HHJ Watson
commented: "these circumstances appear to
me to be relevant to the fairness of enforcing
the judgment sum."
Whilst the true valuation of any sums due to
JRT was an issue for trial, it was likely that at
least substantial elements of JRT's claim for
payment were not properly due to it at the
time it issued the Disputed Payment Notice.
Accordingly, HHJ Watson concluded that it
would be manifestly unjust to TWD if the
judgment was not stayed. TWD would be
forced to pay a potentially overinflated sum,
as a result of which it would be forced into
liquidation and thus unable to pursue its claim
for a declaration that the Disputed Payment
Notice was not a valid payment notice. The
15. WWW.UKADJUDICATORS.CO.UK
NOVEMBER 2020 NEWSLETTER
15 | P a g e
TCC therefore granted a stay of enforcement
pending trial.
Comment
Whilst the general rule remains that an
adjudication award will be enforced, it is clear
that the TCC will make an exception in rare
cases where manifest injustice can be shown.
It is interesting to see that manifest injustice
does not always need to relate to inability to
pay; in this case the TCC clearly took into
account the unusual relationship between the
parties, their conduct throughout the
duration of the contract and the unfairness of
depriving TWD of the opportunity to obtain a
final assessment of the true account. It is
evident that the Court will give short shrift to
parties seeking to take advantage of the
adjudication process in situations where to do
so is clearly unfair.
In the current economic climate, where the
industry is unfortunately likely to see
increased insolvencies, the case serves as
another useful reminder of the limitations of
"smash and grab" adjudication.
James Vernon – Partner T: 020 7469 0424
E: j.vernon@beale-law.com
STATUTORY ADJUDICATION FOR
ALBERTA, CANADA
The proposed legislation was tabled in the
Alberta Legislature October 21, 2020. It will be
debated during the fall 2020 legislative
session.
If the legislation passes, Service Alberta will
work with industry experts to develop
regulations. Service Alberta intends to bring
the new rules into force during July 2021.
The new rules will not apply to contracts
drafted and signed under the existing rules.
They will only apply after the legislation is
proclaimed (currently targeting July 2021).
The new rules will not apply to contracts with
the Government of Alberta, which will
continue to be governed by the Public Works
Act. However, the Government of Alberta will
continue to hold itself to the standards of
prompt payment that are proposed in the
new legislation.
Bill 37: The Builders’ Lien (Prompt Payment)
Amendment Act, 2020 would introduce
timelines and rules for payments and liens in
all construction industry sectors, ensuring
contractors and subcontractors are paid on
time.
Previously, Alberta had no rules for payment
timelines in the construction industry, which
16. WWW.UKADJUDICATORS.CO.UK
NOVEMBER 2020 NEWSLETTER
16 | P a g e
meant these timelines were vague if not
addressed in a contract. If passed, these
changes will set a clear timeline of 28 days for
payments to be received, giving construction
industry professionals the confidence they
need to operate successfully.
The construction industry is a multi-billion
dollar sector of Alberta’s economy that
creates thousands of jobs for Albertans.
Amendments to the act would help ensure
contractors and subcontractors get paid on
time, strengthen Alberta’s economic recovery
and protect jobs.
Key changes
If passed, amendments will:
• set a 28-day timeline for owners,
contractors and subcontractors to pay
invoices
• prohibit ‘pay-when-paid’ clauses in
construction contracts
• ‘pay-when-paid’ clauses allow
contractors to withhold payment
from their subcontractors until the
contractor is paid, unfairly placing the
risk of non-payment onto
subcontractors
• extend timelines for registering liens:
• construction industry: from 45 days to
60 days
• concrete industry: from 45 days to 90
days
• increase the minimum amount owed
that can be subject to a lien from
$300 to $700
• allow dispute resolution through
adjudication, which is faster and less
costly than going to court
• introduce new rules allowing
holdback money on large, multi-year
projects to be released without risk at
pre-set times
• improve subcontractors’ access to
payment information
• rename the Builders’ Lien Act to the
Prompt Payment and Construction
Lien Act
17. WWW.UKADJUDICATORS.CO.UK
NOVEMBER 2020 NEWSLETTER
17 | P a g e
WHAT SUM HAS BEEN NOTIFIED
FOR PAYMENT?
As I sit down to write this piece on sunny but
a cold(ish) autumn morning, prior to a round
of golf (better known as a good old fashioned
hack in my case!) this afternoon, I hope
everybody who reads this piece is coping OK
in these prolonged challenging times and is
keeping themselves and their family, friends,
colleagues and associates safe. If we all look
out for one another then I feel sure we will all
again be able to share in one another’s
pleasurable company in the not too distant
future.
The last 6 months have certainly been the
busiest period I have ever personally
encountered in terms of adjudication
proceedings. The references to adjudication
have been coming to me thick and fast since
March, both as advocate and adjudicator,
with little time to come up for air.
One of the things which has surprised me the
most, recently, is the number of proceedings
in which the responding party has elected not
to serve a response. Prior to the last 6
months it was very rare indeed for me to be
involved in an adjudication where the
responding party has not served a response,
and I think the fact that I have seen this
happening so often recently is definitely a sign
of the times in which we currently find
ourselves. It appears to me that many parties
are not actually disputing that sums are due
for payment, but are merely buying
themselves some additional time in which to
make payment by way of ‘forcing’ the payee
to first go through the adjudication process
before making the payment due. I suspect
this may in part be due to the restrictions
placed on creditors by the Corporate
Insolvency and Governance Act 2020, but that
is a topic for another day.
In this piece, I have considered the view
(which is not necessarily my own) that given
the draconian consequences of failing to
comply with the notice provisions of the Act,
parties seeking payment should be held to a
standard of strict compliance, and so-called
“technical” defences to payment claims
should be permitted. Against that
background, I go to discuss one particular
“technical” defence which, while not
necessarily meritorious, could cause real
problems for a “smash and grab” claimant.
Technical Defences to Payment
Before moving on to discuss two particular
potential arguments which may be used as a
defence to a payment claim where the payer
has failed to serve either of the notices
(payment notice or pay less notice) required
by the amended Construction Act, I quote
Coulson J (as he was then) in Caledonian
Modular Ltd v Mar City Developments Ltd
18. WWW.UKADJUDICATORS.CO.UK
NOVEMBER 2020 NEWSLETTER
18 | P a g e
[2015] EWHC 1855 (TCC) in which he said [at
para 36}
“One of the more baleful effects of the
amendments to the 1996 Act has been a large
increase in the number of cases before
adjudicators (and thus before the TCC), in
which the claimant contractor argues that the
employer failed to serve its notices on time,
and that therefore there was an automatic
right to payment in full of the sum claimed”
[my emphasis added]
and [at para 37]
“In the UK (unlike other jurisdictions with
mandatory construction adjudication, such as
Malaysia) the employer's failure to serve a
payless notice within a short period
challenging the payee's notice can have
draconian consequences. A failure to serve a
notice in time will usually mean a full liability
to pay. That is what the run of recent TCC
cases on this topic, including ISG v Seevic
College [2014] EWHC 4007 (TCC) and Galliford
Try Building Ltd v Estura Ltd [2015] EWHC 412
(TCC), are all about. But it seems to me that, if
contractors want the benefit of these
provisions, they are obliged, in return, to set
out their interim payment claims with proper
clarity. If the employer is to be put at risk that
a failure to serve a payless notice at the
appropriate time during the payment period
will render him liable in full for the amount
claimed, he must be given reasonable notice
that the payment period has been triggered in
the first place” [my emphasis added]
It seems to me that what Lord Justice Coulson
(as he is now) appeared to be saying in
Caledonian Modular is that he viewed the
consequences of failing to serve the notice(s)
required the amended Construction Act as
baleful and draconian therefore, in essence, if
a party wishes to rely upon any such failure in
order to advance a right to payment then it
must, itself, come before the tribunal with
‘clean hands’. In other words, if a party
wishes to rely strictly upon the requirements
of the amended Construction Act, and a
failure to comply with those requirements, in
order to advance a right to payment then it
must, itself, also have complied strictly with
any requirements of the amended
Construction Act.
A particular technical defence: ambiguity in
the notified sum
All of this sets the scene for the particular
potential defence to payment which I discuss
further in this piece.
One of the ‘features’ of applications for
payment which I see on a regular basis (in
those applications submitted by main
contractors, sub-contractors and sub-sub-
contractors alike), both when acting as
advocate and sitting as adjudicator, is the
practice of arriving at the ‘sum due’ by way of
19. WWW.UKADJUDICATORS.CO.UK
NOVEMBER 2020 NEWSLETTER
19 | P a g e
a calculation which takes the cumulative value
of the works undertaken to date and then
deducts the cumulative value of the works
included/claimed in the previous application
for payment.
There is, of course, no issue with this method
of calculation if the payer has paid the
cumulative value of the works
included/claimed in the previous application
for payment. However, what if the payer has
not paid the cumulative value of the works
included/claimed in the previous application
for payment, but has instead actually paid a
lesser sum (for example, the payer has only
paid the cumulative value of the works
included/claimed in the application for
payment prior to the previous application)?
This will lead to the application for payment
being ‘understated’ and there being an
‘underclaim’ and subsequent ‘underpayment’
because the method of calculation assumes
that the value of the works included and
claimed in the previous application for
payment has been paid by the payer.
This is, of course, unlikely to be problematic
where the payer issues the requisite notice(s)
(payment notice and/or pay less notice) in
response to the application for payment.
However, what if the payer fails to issue any
notice at all in response to the application for
payment and the payee wishes to rely upon
its application for payment as a ‘default
notice’? Is the payee entitled only to payment
of the sum stated as due in the application for
payment (which, as aforesaid, has been
calculated by deducting the sum claimed in
the previous application rather than the sum
paid to date), which would, in effect, be an
underpayment? Or is the payee entitled to
have the sum claimed/stated as due in the
application for payment adjusted to account
for the sum which has actually been paid to
date, and which would then, in effect, reflect
the actual payment position?
This is a situation which I have encountered
numerous times, both as an advocate and as
an adjudicator. The correct answer is,
probably, that it depends (isn’t it always
thus??!!).
However, let us for a minute take a fairly
typical example of a contract (such as a JCT
contract) which generally reflects the
requirements of the amended Construction
Act. As most of us will by now be well aware,
following a spate of ‘smash and grab’
adjudications since the floodgates were
opened by Edwards-Stuart J in ISG
Construction Ltd v Seevic College [2014]
EWHC 4007 (TCC), save for limited
circumstances (some of which I discussed in
the Adjudication Society Spring 2019
newsletter), where the payer fails to issue any
notice at all in response to an application for
payment then the sum stated as due in the
application for payment becomes the notified
sum and the payer is obliged to pay that sum
20. WWW.UKADJUDICATORS.CO.UK
NOVEMBER 2020 NEWSLETTER
20 | P a g e
on or before the final date for payment (all as
per sections 110A, 110B and 111 of the
amended Construction Act).
The question which then arises is - what is the
sum stated as due and thus the notified sum?
This then leads to more questions – does the
sum stated as due in the application for
payment (which, remember, in the
circumstances described above has been
calculated by deducting the sum claimed in
the previous application rather than the sum
paid to date and which, in effect, results in an
‘underclaim’) become the notified sum which
the payer is obliged to pay? Is the sum stated
as due in the application for payment actually
the cumulative sum stated therein, with the
notified sum which the payer is obliged to pay
is then being calculated by deducting the sum
paid to date (instead of deducting the
previous application)? Would the notified
sum being something other than the sum
stated as due in the application for payment
not be contrary to Sections 110A, 110B and
111 of the amended Construction Act, which
expressly provide that the sum stated as due
becomes the notified sum which the payer is
obliged to pay if it has not issued a pay less
notice? Is the adjudicator empowered under
paragraph 20 of Part I of the amended
Scheme to ‘correct’ the application for
payment by deducting the sum paid to date
(rather than deducting the previous
application), so to arrive at a different sum
due/notified sum?
I have seen many arguments run in the
circumstances described above. Whilst for
the purposes of this piece I won’t discuss
what were those arguments, what I will
discuss briefly are two arguments which I
haven’t yet seen advanced as a defence by a
payer (I will not divulge whether or not they
are arguments that I have run as advocate
(successfully or otherwise)!).
The arguments are thus –
i) The amended Construction Act (at
sections 110A, 110B and 111) envisages the
notified sum being the sum stated as due in
the relevant notice (be that a payment notice,
or a payee notice in default (such as an
application for payment)). The amended
Construction Act (at section 111) requires the
payer to pay the notified sum if it has not
issued a pay less notice; nothing more,
nothing less. Accordingly, in the
circumstances described above the only sum
which the payer is obliged to pay is the sum
stated as due in the application for payment
(which has become the notified sum, and
which has not been adjusted by a pay less
notice). There is no mechanism by which that
sum can now be adjusted (whether by way of
deducting the sum paid to date instead of the
previous application, or otherwise) to be
something other than that sum; and
21. WWW.UKADJUDICATORS.CO.UK
NOVEMBER 2020 NEWSLETTER
21 | P a g e
ii) In Systems Pipework Ltd v Rotary
Building Services Ltd [2017] EWHC 3235 (TCC)
Coulson J (as he was then) said [at para 31]
“…..it is plain to all that the 2 September 2016
documents did not identify, for example, what
the defendant said had already been paid, or
what the defendant said had been deducted
and/or was now payable by way of retention.
As Mr Sareen put it at paragraph 13 of his
skeleton argument, if the 2 September
documents had notified the amount due, it
would have been quite unnecessary for the
claimant to have to do any calculation at all”;
[my emphasis added]
and [at para 33]
“Neither would the reasonable recipient have
regarded the documents as a notification of
the sum due: for it to be that, the minimum
that was required was the actual
identification of the sum due…..”; [my
emphasis added]
and [at para 35]
“All of this simply goes to confirm the basic
principle that, if X is supposed to be notifying
Y that a sum is due, under a clause that
provides for a deemed agreement that binds
the parties unequivocally, then it is a
prerequisite of the arrangement that the sum
due and the clause are clearly set out in the
relevant notice. It is not good enough to say
that the recipient could have worked it out for
themselves”. [my emphasis added]
Accordingly, in the circumstances described
above the only sum which the payer is obliged
to pay is the sum stated as due in the
application for payment (which has become
the notified sum). There is no mechanism by
which that sum can be adjusted (whether by
way of deducting the sum paid to date instead
of the previous application, or otherwise) to
something other than that sum and, indeed,
any such adjustment would be contrary to the
principles adopted in Systems Pipework.
Let us then assume, for present purposes,
that an adjudicator agrees that the sum which
the payer is obliged to pay in the
circumstances described above is the sum
stated as due in the application for payment
because it is that sum which has become the
notified sum. Can the adjudicator adjust the
sum stated as due in the application for
payment to account for the sum paid to date;
thereby correcting what would otherwise
have been, in effect, an underpayment? If the
adjudication proceedings were being
conducted pursuant to Part I of the amended
Scheme, could the adjudicator utilise the
22. WWW.UKADJUDICATORS.CO.UK
NOVEMBER 2020 NEWSLETTER
22 | P a g e
powers given by paragraph 20 thereof to
make such an adjustment if, in order to
properly do justice, the adjustment was
necessary? If the adjudicator decided that
(s)he did have the power to make such an
adjustment pursuant to that paragraph,
would (s)he not be offending the principles
adopted in Systems Pipework? Should a
distinction now be drawn between the
powers of the adjudicator to make such an
adjustment in a ‘true value’ adjudication (in
which, I would suggest, it is not uncommon
for the actual sum paid to date to be used
when calculating the sum due for payment,
regardless of what is stated in the application
for payment) on the one hand, and the
powers of the adjudicator to make such an
adjustment (or not, as the case may be) in a
‘smash and grab’ adjudication on the other?
To add a further twist to the plot, what about
what O’Farrell J had to say in Kersfield
Developments (Bridge Road) Ltd v Bray and
Slaughter Ltd [2017] EWHC 15 (TCC) [at para
94]?:
“I reject Mr Mort's submission that section
111(8) and the scheme empower an
adjudicator to open up and revise a payment
notice or pay less notice. A payment or pay
less notice is not a decision taken or a
certificate given by any person referred to in
the contract. The notice sets out the sum that
the employer considers is due and payable to
the contractor in response to the contractor's
application”. [emphasis added]
Does O’Farrell J’s judgement in Kersfield
Developments apply equally to a default
payment notice, in that a default payment
notice is not a decision taken or a certificate
given by any person referred to in the
contract, therefore an adjudicator is not
empowered by paragraph 20 of Part I of the
Scheme to open up and revise it? Would the
foregoing not better align with the intention
of sections 110A, 110B and 111 of the
amended Construction Act and Coulson J’s (as
he was then) judgement in Systems
Pipework?
I have my own views on what the answers to
the questions posed above should be, but in
the current circumstances perhaps we may
see the courts grapple with these questions in
the not too distant future; therefore, I shall
keep my powder dry for the time being and
leave you to form your own views.
Alternatively, you may well discover my views
should you come before me when I am sitting
as adjudicator!
Dean Sayers is a Director with Sayers
Commercial Ltd, and is available to sit as an
adjudicator and arbitrator
dean@sayerscommercial.co.uk
23. WWW.UKADJUDICATORS.CO.UK
NOVEMBER 2020 NEWSLETTER
23 | P a g e
TCC COURT JUDGEMENTS
September
• Daewoo Shipbuilding And Marine
Engineering Company Ltd v Songa
Offshore Equinox Ltd & Anor [2020]
EWHC 2353 (TCC) (01 September
2020)
• Dr Jones Yeovil Ltd v The Stepping
Stone Group Ltd [2020] EWHC 2308
(TCC) (04 September 2020)
• Energy Works (Hull) Ltd v MW High
Tech Projects UK Ltd & Ors [2020]
EWHC 2537 (TCC) (24 September
2020)
• Essex County Council v UBB Waste
(Essex) Ltd (No. 3) [2020] EWHC 2387
(TCC) (11 September 2020)
• John Doyle Construction Ltd v Erith
Contractors Ltd (Rev 1) [2020] EWHC
2451 (TCC) (14 September 2020)
• The Leicester Bakery (Holdings) Ltd v
Ridge And Partners LLP (Rev 1) [2020]
EWHC 2430 (TCC) (11 September
2020)
• Municpio De Mariana & Ors v BHP
Group Plc & Anor [2020] EWHC 2471
(TCC) (18 September 2020)
• Premier Engineering (Lincoln) Ltd v
MW High Tech Projects UK Ltd [2020]
EWHC 2484 (TCC) (18 September
2020)
• Pullman Foods Ltd v The Welsh
Ministers & Anor [2020] EWHC 2521
(TCC) (23 September 2020)
October
• BDW Trading Ltd v Lantoom
Ltd [2020] EWHC 2744 (TCC) (16
October 2020)
• Blue Manchester Ltd v North West
Ground Rents Ltd [2020] EWHC 2777
(TCC) (20 October 2020)
24. WWW.UKADJUDICATORS.CO.UK
NOVEMBER 2020 NEWSLETTER
24 | P a g e
FORTHCOMING LECTURES
03/11/2020 Online 5.30pm
“The joint First Prize Winners of the Hudson
Prize
Competition will present their award winning
papers”
Speakers: Anson Cheung and Serena Lee
19/11/2020 Online 5.00pm
“Case Law | Adjudication update”
(excluding Bresco and Doyle v Erith)
Speaker: Steven Walker QC
23/11/2020 Online 5.00pm
“Construction Hearings: some practical
issues”
Speakers: Nicola Dunleavy and Andrew Miller
QC
30/11/2020 Online 5.00pm
“2020 Irish Conference Keynote Lecture”
Speaker: Anneliese Day QC
01/12/2020 Online 4.30pm
“Pre-trial Process and Construction Disputes”
Speakers: Karen Killoran, Alan Brady BL
and Leon Major
01/12/2020 Online 6.30pm
“Britain's greatest building project - Hadrian's
Wall”
Speaker: Sir Rupert Jackson
02/12/2020 Online 4.30pm
“Third Party Funding in Construction Law”
Speakers: Matthew Denney and Darren
Lehane S.C
25. WWW.UKADJUDICATORS.CO.UK
NOVEMBER 2020 NEWSLETTER
25 | P a g e
3/12/2020 Online 5.00pm
“Deep Technology & Construction Law
Disputes”
Speakers: Mark Beer and Bruno Herbots
4/12/2020 Online 5.00pm
“Adjudication 2020
Speakers: Graeme Sampson, James
O’Donoghue
and Damien Keogh
9/12/2020 Online 5.00pm
“Enforcement after Bresco”
Speaker: Riaz Hussain QC
https://www.scl.org.uk/events
SCL INTERNATIONAL CONFERENCE
2021
The Society of Construction Law 9th
International Conference has been postponed
till November 2021.
The Right Honourable Lord Justice Coulson
will be a keynote speaker at the Conference.
http://www.constructionlaw2021.com/scl21
26. WWW.UKADJUDICATORS.CO.UK
NOVEMBER 2020 NEWSLETTER
26 | P a g e
i
Bridgeway Construction Ltd v Tolent Construction
Ltd (2000) CILL 1662
ii
Yuanda (UK) Co Ltd v WW Gear Construction Ltd
[2010] EWHC 720
iii
Lulu Construction Ltd v Mulalley & Co Ltd. [2016]
EWHC 1852
iv
Housing Grants, Construction and Regeneration
Act 1996
v
Allied P&L Ltd v Paradigm Housing Group Ltd
[2009] EWHC 2890
vi
Enviroflow Management Ltd v Redhill Works
(Nottingham) Ltd (2017) [unreported]
vii
EU Directive 2011/7/EU