www.fgks.org   »   [go: up one dir, main page]

SlideShare a Scribd company logo
Proposals for a subcontractor’s
escape from a conditional clause
Antonios
Dimitracopoulos
Bin Shabib &
Associates, UAE
Types of conditional clauses
Conditional clauses can be broadly divided
into two categories, namely ‘pay when paid’
and, ‘pay if paid’ clauses.
Pay when paid clauses generally contain a
condition such that payment by the main
contractor to the subcontractor will be
dependent upon payment being first received
by the main contractor from the employer.
The main purpose of a pay when paid
clause is to defer payment to a point in time
The common practice is that the main contractor will contractually delegate various elements of
its works to specialist subcontractors. Such subcontractors may be sourced and chosen by the
main contractor or may be specifically nominated by the employer.
The UAE Civil Code1
at Article 8902
expressly provides for the right of the main contractor to
subcontract, provided there are no contractual terms preventing this in the main contract.
Therefore, main contractors are potentially exposed to making payments to their subcontractors
when they have not themselves received the corresponding payments from the employer.
Main contractors, therefore, often include conditional payment clauses in subcontracts so as to
confer payment related risks onto the subcontractor.
that is determined by a specific event, namely
payment by the employer to the contractor.
The occurrence of pay if paid clauses in
the UAE is relatively uncommon. In general,
whenever pay if paid clauses are included in
subcontracts internationally, they may
amount to specific wording that aims to
clarify that a shift of the risk of non-payment
has been agreed to. Instances of pay if paid
clauses, identified in primarily US cases, can
be focused particularly on clearly and
aggressively reflecting the parties’ intentions.
CONSTRUCTION LAW INTERNATIONAL Volume 10 Issue 2 June 2015	 25
SUBCONTRACTOR’S ESCAPE
As indicated above, the intention of pay if
paid clauses depends on the eventuality
rather than on deferring the timing of
payment and to shift the risk of non-payment
from the main contractor to the
subcontractor.
UAE statutory law background to
conditional payment structures in
construction
UAE law provides a protective barrier for
the employer and confirms, in the Muqawala
section of the UAE Civil Code, Article 891,
that no claim may be addressed by the
subcontractor to the employer, save for
instances of assignment.3
This being the position, one must ask what
consideration does the subcontractor enjoy
in return for this unenviable shift in
risk-taking that conditional clauses impose?
For conditional clauses to have a fair sense
of purpose in a subcontract, the answer to
that question must revolve around the
following:
•	 the main contractor is obliged to adopt the
subcontractor’s claims for payment as if the
claims were its own;
•	 to the extent it considers the claims valid,
the main contractor must then pursue them
with the employer, again as if they were its
own; and
•	any failure to do so should prohibit the
main contractor from relying on any
conditional clause, thus rendering it
directly accountable to the subcontractor.
In terms of legal authority, the concept of
conditional payments seems to fall squarely
within the ambit of Part 3, Section 1 of the
UAE Civil Code, relating to ‘Dispositions
conditional by suspension or deferment’,4
Article 428 of which supports the view that if
the performance of an obligation is subject
to a condition, then efforts must be made for
that condition to be observed.5
It is not relevant how much time has passed
since payment to the subcontractor became
due, but rather what can be proven to have
taken place during such time. This would
appear to be a more dominant driver in
determining the operation of a conditional
clause under UAE law.
By contrast, if it can be shown that no
demonstrable efforts (in the context of
Article 428) have been made to observe the
condition, then it would be arguable under
UAE law that the main contractor can no
longer rely on a conditional pay when paid
clause and that to effectively avoid making
payment to the subcontractor, it would have
to resort to more substantive defences.
As will be seen below, recent UAE
jurisprudence has indicated that, in the
presence of a conditional clause, a claim
against the main contractor based purely on
a breach of the subcontract for non-payment
is likely to fail.
UAE jurisprudence
Whilst many disputes arising out of
subcontracts will be referred to private and
confidential arbitration, there have been a
few instances where an arbitration clause was
absent and litigation ensued.
From the cases readily reported, save one
case in 1995 where a distinction was made
by the Dubai courts on whether a project
had been completed or not6
before a
conditional payment clause could be relied
upon, most subsequent cases7
upheld the
validity of a pay when paid clause and
rejected the claims filed by the
subcontractors on the basis of them being
premature.Inonesuchcase,8
theapplication
of conditional payment clauses in a
subcontract was analysed as follows:
•	the contractor imposed a condition that
payments to the subcontractor would be
paid when such moneys from the employer
were paid;
•	this is an obligation suspended until the
conditional fact materialised; and
•	 the subcontractor, therefore, did not have
the right to claim the balance of its dues
until the condition was met, that is, payment
was received by the main contractor from
the employer.
In all these cases, the subcontractor’s claims
were made on the simple basis of a breach
of contract for non-payment. They were not
based on an argument that the true breach
was that the main contractor had failed to
pursue fully the subcontractor’s claims against
When faced with a
conditional payment clause,
the subcontractor’s main
strategy in pursuing its claims
against the main contractor is
one of timing
26	 CONSTRUCTION LAW INTERNATIONAL Volume 10 Issue 2 June 2015
the employer. Nor were they based on the
employer having rejected such claims, thus
containing the dispute strictly between the
main contractor and the subcontractor. The
subcontractor’s position was countered by a
straightforward application of Article 420 of
the UAE Civil Code,9
in that the condition
precedent (of payment by the employer) had
not yet occurred.
Alternative bases for the
subcontractor to pursue its claims
In light of the above, and given the factors set
out below, we explore two alternative bases
upon which a subcontractor can successfully
pursue its claims against the main contractor,
including whether the timing of any actions it
needs to take to achieve this:
•	 pay if paid clauses are relatively rare in the
UAE;
•	 pay when paid clauses defer the timing of
payment;
•	the UAE Civil Code acknowledges that
some effort must be made for a condition
to materialise; and
•	that the consideration that the
subcontractor must enjoy is the main
contractor’s obligation of pursuing the
subcontractor’s claims.
Direct payment agreements with the
employer
Although the ability for subcontractors to
successfully negotiate the terms of their
subcontract are usually very limited, we
have seen instances where nominated
subcontractors managed to extract a direct
payment obligation by the employer, at least
for certified amounts, thus bypassing the
main contractor.
This option is also envisaged by UAE
law, in the Muqawala section of the Civil
Code,10
as a possible exception to be
executed by way of assigning the obligation
to pay the subcontractor from the
contractor to the employer.
Two issues are of note in instances where
direct payment mechanisms have been
attempted in the UAE:
•	 thestandardobligationofthemaincontractor
to effect payment to the subcontractor (on
a pay when paid basis) is often not removed
from either of the two subcontracts; and
•	court proceedings that are normally
brought by the subcontractor against both
the employer and the main contractor
have resulted in the court ordering the
subcontractor to proceed first to arbitration
under the subcontract against the main
contractor and, if that were to fail or result
in non-payment, then – and only then –
could the subcontractor proceed in court
against the employer under the direct
payment agreement.
Direct payment agreements are seldom
well-coordinated with the contents of either
the main contract or the subcontract and
commonly serve as a tool for the employer
to deflect liability for the subcontractor’s
payments onto the main contractor and
vice versa.
Lack of pursuit of subcontractor’s claims
A further option for the subcontractor
is to argue that the true breach lies in
the main contractor failing to pursue the
subcontractor’s claims against the employer
to the fullest extent permissible by law. The
instances where the subcontractor could
legitimately argue this include:
•	when the employer has rejected the
subcontractor’s claim, the main contractor
has not accepted such rejection, but has
failed to pursue the matter by way of a
dispute resolution process or otherwise; or
•	 when the employer has deferred payment
to an indefinite point in time that can
no longer be considered reasonable and
the main contractor again fails to pursue
the matter whether by way of a dispute
resolution process or otherwise.
Article 428 of the UAE Civil Code sets out the
degree to which fulfilment of the condition
must be pursued. This lends itself to an
argument that a main contractor’s failure
to pursue the subcontractor’s claims could
effectively amount to a failure to observe the
condition (of payment by the employer) to
the maximum degree possible.
In the presence of a conditional clause, it is… unwise for the
subcontractor to commence legal proceedings against the main
contractor on the simple basis of a debt collection exercise
CONSTRUCTION LAW INTERNATIONAL Volume 10 Issue 2 June 2015	 27
SUBCONTRACTOR’S ESCAPE
One must be mindful of the fact that main
contractors would commonly be reluctant to
start a dispute resolution process against an
employer purely in order to pursue their
subcontractors’ claims. In demonstrating such
reluctance, the main contractor may argue:
•	 that at the stage the subcontractor’s action
commenced, it would be unreasonable for it
(the main contractor) to have commenced
legal proceedings; or
•	that this may be supported by reference
to various commercial or contractual
considerations.
Whichever option the main contractor
adopts, it is likely that if pursuit of the
subcontractor’s claim is to be argued as a
condition precedent for any conditional
SEQUENCE TIMING S/C’s REQUEST/DEMAND BASIS
A
When invoices become
overdue.
Payment of its outstanding invoices/
dues.
Contractual.
B
When negative reply is
received from main contractor
(MC) on first request.
Evidence of inclusion of its work in
monthly invoices to Employer (E).
Contractual/correspondence based.
C
Once evidence of inclusion
in monthly invoices/final
statement of accounts has
been provided.
Evidence of rejection of payment by E. Contractual/correspondence based.
D
Pay when paid (PWP): once
confirmation of E’s rejection
and MC’s agreement to this is
obtained.
Payment of dues by MC.
Legal: impossibility of condition, Article 423
of Civil Code.
E
Pay if paid (PIP)/PWP: whether
or not E has rejected payment
& whether or not MC has
contested any rejection by E.
Evidence of pursuit of payment.
Legal: lack of pursuit, Articles 420 and 428
of Civil Code.
F
Once the scope of
subcontractor’s (SC) work has
been completed.
Evidence of pursuit of payment.
Legal: lack of pursuit, Articles 420 and 428
of Civil Code.
G
Again when the project has
been handed over.
Evidence of pursuit of payment.
Legal: lack of pursuit, Articles 420 and 428
of Civil Code.
H
Again when the defects
liability period has expired.
Evidence of pursuit of payment.
Legal: lack of pursuit, Articles 420 and 428
of Civil Code.
I
When negative reply is
received from MC on the
above request.
Evidence of a legal notice issued for
amounts inclusive of the subcontractor’s
dues.
Legal: Lack of pursuit, Articles 420 and 428
of Civil Code.
J When the deadline of a legal
notice expires.
Evidence of legal proceedings having
been commenced.
Legal: Lack of pursuit, Articles 420 and 428
of Civil Code.
clause to be relied upon, then such condition
could be easily satisfied in most instances,
save for the case of the main contractor
formally commencing legal proceedings
against the employer.
Employer’s outright rejection of a
subcontractor’s claim
As indicated above, instances of an outright
rejection by the employer of a main
contractor’s claim that includes or relates to
the subcontractor’s works would convert the
question of when payment would be made to
a definite non-payment.
In terms of how this can be
accommodated within the confines of
28	 CONSTRUCTION LAW INTERNATIONAL Volume 10 Issue 1 March 2015

Recommended for you

Assignment #12 -hajer al rubaiai ( business) (1)
Assignment #12  -hajer al rubaiai ( business) (1)Assignment #12  -hajer al rubaiai ( business) (1)
Assignment #12 -hajer al rubaiai ( business) (1)

This document provides an overview of business contracts and torts under Omani law. It analyzes two legal cases. The first case involves a singer, Mr. Badar, who failed to attend required rehearsals for a musical performance due to illness. The event organizer, Mr. Yosuf, terminated their contract. Analyzing Omani contract law, the termination was likely valid as Mr. Badar broke a key term of the agreement. The second case involves a construction dispute that raises issues of negligence and liability. The document provides advice to each party based on the relevant Omani laws.

IJAA Vol 7 No. 2 - Hazem Hussein -
IJAA Vol 7 No. 2 - Hazem Hussein -IJAA Vol 7 No. 2 - Hazem Hussein -
IJAA Vol 7 No. 2 - Hazem Hussein -

1. Effective multi-party arbitration clauses in construction contracts require properly drafting the clause to encompass all potential disputes between related parties to the construction project under one proceeding. 2. Back-to-back agreements between contractors and subcontractors are important to ensure subcontractor obligations match those in the main contract. However, contractors sometimes fail to secure these agreements. 3. Independent dispute resolution clauses are needed in the main contract and any subcontracts. Awards from arbitrations between the client and contractor would not necessarily bind the subcontractor in separate arbitrations between the contractor and subcontractor.

Commercial law
Commercial law Commercial law
Commercial law

The document discusses various aspects of contract performance and discharge under commercial law in India. It covers the meaning of performance and discharge of a contract, modes of discharge such as performance, agreement, impossibility, lapse of time and operation of law. It also discusses remedies for breach of contract, including rescission, specific performance, injunction, quantum meruit and damages.

commercial lawpresentation
UAE law, Articles 420–428 of the UAE
Civil Code deal with ‘Dispositions
conditional by suspension or deferment’,
essentially relating to conditional clauses.
The main contractor’s options in instances
of outright rejection by the employer would
be to:
•	 challenge the merits of the subcontractor’s
entitlement (rather than simply its timing)
and adopt arguments raised by the
employer/engineer;
•	 challenge the merits of the subcontractor’s
entitlement (rather than simply its timing)
and produce its own arguments for doing so;
or
•	challenge the employer’s rejection,
pursuing claims that would include those
of the subcontractor.
Which option the main contractor adopts
can be of critical relevance to the application
of either a pay when paid clause or a pay if
paid clause.
Pay when paid clauses are based on a
presumption that payment would eventually
be made. They would, therefore, become
inapplicable if the employer refused to pay,
for the simple reason that for the main
contractor to rely on them, it would have to
unilaterally convert the condition of ‘when’
to a condition of ‘if/whether’.
Timing as a key factor to a
subcontractor’s strategy
When being faced with a conditional payment
clause, the subcontractor’s main strategy in
pursuing its claims against the main contractor
is one of timing. Therefore, a subcontractor
that is deprived of its dues should sequence
its approach to a conditional payment clause
by documenting its requests as follows.
Once the main contractor is forced to file a
legal action against the employer, the
subcontractor’s claims against the main
contractor are effectively carried over onto
an action against the employer. Whilst the
subcontractor can have little control over
suchproceedings(unlessthemaincontractor
encourages them to assist), the conditional
clause will have been given the purpose and
substance that the parties intended.
On the assumption that an award or
judgment is eventually issued and, despite
the main contractor’s perceived best efforts,
the subcontractor’s claims (or any part
thereof) are not awarded, the question arises
whether this would be the end of the road for
the subcontractor. The answer to this
question would depend a lot more on what
the reason is behind the employer’s
exoneration, rather than on whether the
subcontract contained a pay if paid or a pay
when paid clause.
Conclusion
In the presence of a conditional clause, it is
generally accepted that it is unwise for the
subcontractor to commence legal proceedings
against the main contractor on the simple
basis of a debt collection exercise as it is
unlikely to succeed.
Ironically, the more unopposed (by the main
contractor) a subcontractor’s claim is, the
more difficult it is to control the payment
process and the more hindered it is by a
conditional clause. Conversely, any direct
challenge to its claims by the main contractor
may block the triggering of a conditional
clause, thus making the dispute resolution
process an affair that is confined solely between
the main contractor and the subcontractor.
Finally, the question of whether a
subcontractor can pursue its claims against the
main contractor, even after the employer has
been exonerated of any liability, will depend
more on the reasons behind this, rather than
on the nature of the conditional clause.
Notes
1		Federal Law No 1/1987.
2		 An English translation of which states: ‘(1) A contractor
may entrust the performance of the whole or part of
the work to another contractor unless he is prevented
from so doing by a condition of the contract, or unless
the nature of the work requires that he do it in person.
(2) The first contractor shall remain liable as towards
the employer.’
3		An English translation states that: ‘Article 891:
A sub-contractor shall have no claim against the
employer for anything due to him from the first
contractor unless he has made an assignment to him
against the employer.’
4		Arts 420–428 of the Civil Code.
5		 An English translation states: ‘Article 428: A Condition
must be observed as far as is possible.’
6		Dubai Court of Cassation Case No 281 of 1995: the
distinction related to an obligation by the main
contractor to pay the subcontractor, despite a
conditional clause, if the project has been completed.
7		Dubai Court of Cassation Case No 267 of 2007, Dubai
Court of Cassation Case No 83 of 2009.
8		Dubai Court of Cassation Case No 240 of 2006.
9		An English translation of which provides that: ‘Article
420: A Condition is a future matter upon the existence
or absence of which the full effectiveness (of a
disposition) depends.’
10	Art 891, as previously mentioned.
Antonios
Dimitracopoulos
MCIArb is a partner
with Bin Shabib &
Associates, practising
in the UAE since 1995.
He is dually qualified as
a solicitor of the Senior
Courts of England &
Wales and a Greek
attorney at law and a
registered arbitrator
with the Dubai
International
Arbitration Centre. His
practice focuses on all
aspects of dispute
resolution within the
local construction
industry, often acting
for subcontractors. He
has rights of audience
before the DIFC courts
and extensive
experience in both
UAE litigation and
arbitration. He can be
contacted at antonios.
dimitracopoulos@
bsa.ae.
CONSTRUCTION LAW INTERNATIONAL Volume 10 Issue 2 June 2015	 29

More Related Content

What's hot

Calling of a demand guarantee
Calling of a demand guaranteeCalling of a demand guarantee
Calling of a demand guarantee
Andrea Frosinini
 
FORCE MAJEURE CLAUSE: RELEVANCE AND APPLICABILITY IN THE WAKE OF COVID – 19 A...
FORCE MAJEURE CLAUSE: RELEVANCE AND APPLICABILITY IN THE WAKE OF COVID – 19 A...FORCE MAJEURE CLAUSE: RELEVANCE AND APPLICABILITY IN THE WAKE OF COVID – 19 A...
FORCE MAJEURE CLAUSE: RELEVANCE AND APPLICABILITY IN THE WAKE OF COVID – 19 A...
Hitendra Hiremath
 
Law of contract
Law of contractLaw of contract
Law of contract
Ncell
 
Assignment #12 -hajer al rubaiai ( business) (1)
Assignment #12  -hajer al rubaiai ( business) (1)Assignment #12  -hajer al rubaiai ( business) (1)
Assignment #12 -hajer al rubaiai ( business) (1)
projectname
 
IJAA Vol 7 No. 2 - Hazem Hussein -
IJAA Vol 7 No. 2 - Hazem Hussein -IJAA Vol 7 No. 2 - Hazem Hussein -
IJAA Vol 7 No. 2 - Hazem Hussein -
Hazem Hussien Dr.
 
Commercial law
Commercial law Commercial law
Commercial law
Sharmila Devi
 
Commercial law part 2
Commercial law part 2Commercial law part 2
Commercial law part 2
jeyapriyav
 
Zenrock Counterfeit Commodity Credit
Zenrock Counterfeit Commodity CreditZenrock Counterfeit Commodity Credit
Zenrock Counterfeit Commodity Credit
GE 94
 
Insolvency Resolution Process of Guarantors under IBC
Insolvency Resolution Process of Guarantors under IBCInsolvency Resolution Process of Guarantors under IBC
Insolvency Resolution Process of Guarantors under IBC
Karan Valecha
 
LBE-1.2.pptx
LBE-1.2.pptxLBE-1.2.pptx
LBE-1.2.pptx
nirajchaudhari27
 
William Kosar What Every Budget Officer Should Know_Rwanda
William Kosar What Every Budget Officer Should Know_RwandaWilliam Kosar What Every Budget Officer Should Know_Rwanda
William Kosar What Every Budget Officer Should Know_Rwanda
William Kosar
 
Legal aspect of business
Legal aspect of businessLegal aspect of business
Legal aspect of business
Zubair Ahmad
 
The indian contract act 1971
The indian contract act 1971The indian contract act 1971
The indian contract act 1971
gythorat
 
Bankruptcy Act 1997 (By BU AIS 2nd Batch)
Bankruptcy Act 1997 (By BU AIS 2nd Batch)Bankruptcy Act 1997 (By BU AIS 2nd Batch)
Bankruptcy Act 1997 (By BU AIS 2nd Batch)
Jessic Sharif
 
Presentation aditi duggal
Presentation aditi duggalPresentation aditi duggal
Presentation aditi duggal
Aditi Duggal
 
Contracts With The Government
Contracts With The GovernmentContracts With The Government
Contracts With The Government
Prof. (Dr.) Tabrez Ahmad
 
A Guide to Private Finance in Myanmar
A Guide to Private Finance in MyanmarA Guide to Private Finance in Myanmar
A Guide to Private Finance in Myanmar
Dr. Oliver Massmann
 
Non Compete Covenants
Non Compete CovenantsNon Compete Covenants
Non Compete Covenants
Kevin Robin
 
Lawyer in Vietnam Oliver Massmann REAL ESTATE – FOREIGNERS BUYING PROPERTY ...
  Lawyer in Vietnam Oliver Massmann REAL ESTATE – FOREIGNERS BUYING PROPERTY ...  Lawyer in Vietnam Oliver Massmann REAL ESTATE – FOREIGNERS BUYING PROPERTY ...
Lawyer in Vietnam Oliver Massmann REAL ESTATE – FOREIGNERS BUYING PROPERTY ...
Dr. Oliver Massmann
 
Contract
ContractContract
Contract
Mamta Bisht
 

What's hot (20)

Calling of a demand guarantee
Calling of a demand guaranteeCalling of a demand guarantee
Calling of a demand guarantee
 
FORCE MAJEURE CLAUSE: RELEVANCE AND APPLICABILITY IN THE WAKE OF COVID – 19 A...
FORCE MAJEURE CLAUSE: RELEVANCE AND APPLICABILITY IN THE WAKE OF COVID – 19 A...FORCE MAJEURE CLAUSE: RELEVANCE AND APPLICABILITY IN THE WAKE OF COVID – 19 A...
FORCE MAJEURE CLAUSE: RELEVANCE AND APPLICABILITY IN THE WAKE OF COVID – 19 A...
 
Law of contract
Law of contractLaw of contract
Law of contract
 
Assignment #12 -hajer al rubaiai ( business) (1)
Assignment #12  -hajer al rubaiai ( business) (1)Assignment #12  -hajer al rubaiai ( business) (1)
Assignment #12 -hajer al rubaiai ( business) (1)
 
IJAA Vol 7 No. 2 - Hazem Hussein -
IJAA Vol 7 No. 2 - Hazem Hussein -IJAA Vol 7 No. 2 - Hazem Hussein -
IJAA Vol 7 No. 2 - Hazem Hussein -
 
Commercial law
Commercial law Commercial law
Commercial law
 
Commercial law part 2
Commercial law part 2Commercial law part 2
Commercial law part 2
 
Zenrock Counterfeit Commodity Credit
Zenrock Counterfeit Commodity CreditZenrock Counterfeit Commodity Credit
Zenrock Counterfeit Commodity Credit
 
Insolvency Resolution Process of Guarantors under IBC
Insolvency Resolution Process of Guarantors under IBCInsolvency Resolution Process of Guarantors under IBC
Insolvency Resolution Process of Guarantors under IBC
 
LBE-1.2.pptx
LBE-1.2.pptxLBE-1.2.pptx
LBE-1.2.pptx
 
William Kosar What Every Budget Officer Should Know_Rwanda
William Kosar What Every Budget Officer Should Know_RwandaWilliam Kosar What Every Budget Officer Should Know_Rwanda
William Kosar What Every Budget Officer Should Know_Rwanda
 
Legal aspect of business
Legal aspect of businessLegal aspect of business
Legal aspect of business
 
The indian contract act 1971
The indian contract act 1971The indian contract act 1971
The indian contract act 1971
 
Bankruptcy Act 1997 (By BU AIS 2nd Batch)
Bankruptcy Act 1997 (By BU AIS 2nd Batch)Bankruptcy Act 1997 (By BU AIS 2nd Batch)
Bankruptcy Act 1997 (By BU AIS 2nd Batch)
 
Presentation aditi duggal
Presentation aditi duggalPresentation aditi duggal
Presentation aditi duggal
 
Contracts With The Government
Contracts With The GovernmentContracts With The Government
Contracts With The Government
 
A Guide to Private Finance in Myanmar
A Guide to Private Finance in MyanmarA Guide to Private Finance in Myanmar
A Guide to Private Finance in Myanmar
 
Non Compete Covenants
Non Compete CovenantsNon Compete Covenants
Non Compete Covenants
 
Lawyer in Vietnam Oliver Massmann REAL ESTATE – FOREIGNERS BUYING PROPERTY ...
  Lawyer in Vietnam Oliver Massmann REAL ESTATE – FOREIGNERS BUYING PROPERTY ...  Lawyer in Vietnam Oliver Massmann REAL ESTATE – FOREIGNERS BUYING PROPERTY ...
Lawyer in Vietnam Oliver Massmann REAL ESTATE – FOREIGNERS BUYING PROPERTY ...
 
Contract
ContractContract
Contract
 

Viewers also liked

Самігуліна "Варіації та рондо"
Самігуліна "Варіації та рондо"Самігуліна "Варіації та рондо"
Самігуліна "Варіації та рондо"
Netteka Bezuhla
 
Eccellenze in digitale - Certificato
Eccellenze in digitale - CertificatoEccellenze in digitale - Certificato
Eccellenze in digitale - Certificato
Daniele Brolli
 
Lawlink com profile_18230
Lawlink com profile_18230Lawlink com profile_18230
Lawlink com profile_18230
PuzzledFarmer574
 
Vela fregolina 2009 2
Vela fregolina 2009 2Vela fregolina 2009 2
Vela fregolina 2009 2
José Manuel García Esteban
 
Interbrand-Best-Global-Brands-2013
Interbrand-Best-Global-Brands-2013Interbrand-Best-Global-Brands-2013
Interbrand-Best-Global-Brands-2013
Erica Velis
 
Upc
UpcUpc
Presentatie Nutrion & Health claims maastricht 2007
Presentatie Nutrion & Health claims maastricht 2007Presentatie Nutrion & Health claims maastricht 2007
Presentatie Nutrion & Health claims maastricht 2007
Wouter de Heij
 
Centro regional de formación de profesores de castilla
Centro regional de formación de profesores de castillaCentro regional de formación de profesores de castilla
Centro regional de formación de profesores de castilla
Carol de la Plaza
 
Voeding en gezondheid en business 2009
Voeding en gezondheid en business 2009Voeding en gezondheid en business 2009
Voeding en gezondheid en business 2009
Wouter de Heij
 
FLEXOWINE-250-350-410
FLEXOWINE-250-350-410FLEXOWINE-250-350-410
FLEXOWINE-250-350-410
M-TECH Print
 
Ole ole bandung-na-nb_dok.tunas63
Ole ole bandung-na-nb_dok.tunas63Ole ole bandung-na-nb_dok.tunas63
Ole ole bandung-na-nb_dok.tunas63
Yadhi Muqsith
 
Kawahira, Casey - Portfolio,linked
Kawahira, Casey - Portfolio,linkedKawahira, Casey - Portfolio,linked
Kawahira, Casey - Portfolio,linked
Casey Kawahira
 
Al fauzul azeem fi salat ala nabi ill kareem by syed muhammad usman makki
Al fauzul azeem fi salat ala nabi ill kareem by syed muhammad usman makkiAl fauzul azeem fi salat ala nabi ill kareem by syed muhammad usman makki
Al fauzul azeem fi salat ala nabi ill kareem by syed muhammad usman makki
Muhammad Tariq
 
Safety Relief Valve sizing, selection & quotation software
Safety Relief Valve sizing, selection & quotation software Safety Relief Valve sizing, selection & quotation software
Safety Relief Valve sizing, selection & quotation software
Sanjeev Nadkarni
 
Digipack Analysis
Digipack AnalysisDigipack Analysis
Digipack Analysis
jack_brady
 

Viewers also liked (15)

Самігуліна "Варіації та рондо"
Самігуліна "Варіації та рондо"Самігуліна "Варіації та рондо"
Самігуліна "Варіації та рондо"
 
Eccellenze in digitale - Certificato
Eccellenze in digitale - CertificatoEccellenze in digitale - Certificato
Eccellenze in digitale - Certificato
 
Lawlink com profile_18230
Lawlink com profile_18230Lawlink com profile_18230
Lawlink com profile_18230
 
Vela fregolina 2009 2
Vela fregolina 2009 2Vela fregolina 2009 2
Vela fregolina 2009 2
 
Interbrand-Best-Global-Brands-2013
Interbrand-Best-Global-Brands-2013Interbrand-Best-Global-Brands-2013
Interbrand-Best-Global-Brands-2013
 
Upc
UpcUpc
Upc
 
Presentatie Nutrion & Health claims maastricht 2007
Presentatie Nutrion & Health claims maastricht 2007Presentatie Nutrion & Health claims maastricht 2007
Presentatie Nutrion & Health claims maastricht 2007
 
Centro regional de formación de profesores de castilla
Centro regional de formación de profesores de castillaCentro regional de formación de profesores de castilla
Centro regional de formación de profesores de castilla
 
Voeding en gezondheid en business 2009
Voeding en gezondheid en business 2009Voeding en gezondheid en business 2009
Voeding en gezondheid en business 2009
 
FLEXOWINE-250-350-410
FLEXOWINE-250-350-410FLEXOWINE-250-350-410
FLEXOWINE-250-350-410
 
Ole ole bandung-na-nb_dok.tunas63
Ole ole bandung-na-nb_dok.tunas63Ole ole bandung-na-nb_dok.tunas63
Ole ole bandung-na-nb_dok.tunas63
 
Kawahira, Casey - Portfolio,linked
Kawahira, Casey - Portfolio,linkedKawahira, Casey - Portfolio,linked
Kawahira, Casey - Portfolio,linked
 
Al fauzul azeem fi salat ala nabi ill kareem by syed muhammad usman makki
Al fauzul azeem fi salat ala nabi ill kareem by syed muhammad usman makkiAl fauzul azeem fi salat ala nabi ill kareem by syed muhammad usman makki
Al fauzul azeem fi salat ala nabi ill kareem by syed muhammad usman makki
 
Safety Relief Valve sizing, selection & quotation software
Safety Relief Valve sizing, selection & quotation software Safety Relief Valve sizing, selection & quotation software
Safety Relief Valve sizing, selection & quotation software
 
Digipack Analysis
Digipack AnalysisDigipack Analysis
Digipack Analysis
 

Similar to CLI ARTICLE ON SUBCONTRACTING

Subcontract Clauses.PPTX
Subcontract Clauses.PPTXSubcontract Clauses.PPTX
Subcontract Clauses.PPTX
Ryan Hatton
 
Business laws
Business lawsBusiness laws
Business laws
Chandresh Madhyan
 
Recent Trends In Guarantees
Recent Trends In GuaranteesRecent Trends In Guarantees
Recent Trends In Guarantees
Barrister & Solicitor
 
Clause 4.2 Performance Security-Understanding Clauses in FIDIC ‘Conditions of...
Clause 4.2 Performance Security-Understanding Clauses in FIDIC ‘Conditions of...Clause 4.2 Performance Security-Understanding Clauses in FIDIC ‘Conditions of...
Clause 4.2 Performance Security-Understanding Clauses in FIDIC ‘Conditions of...
Divyanshu Dayal
 
Loan transfer
Loan transferLoan transfer
Loan transfer
Natalia Abtseshko
 
C ps, css, rep & warranties
C ps, css, rep & warrantiesC ps, css, rep & warranties
C ps, css, rep & warranties
IrinaTyan
 
Be aware of the legal consequences of issuing guarantee cheques in uae
Be aware of the legal consequences of issuing guarantee cheques in uaeBe aware of the legal consequences of issuing guarantee cheques in uae
Be aware of the legal consequences of issuing guarantee cheques in uae
Dr. Hassan Mohsen
 
Clause 16 suspension
Clause 16 suspensionClause 16 suspension
Clause 16 suspension
breyerhanna
 
Specific performance, can parties contract out
Specific performance, can parties contract outSpecific performance, can parties contract out
Specific performance, can parties contract out
joseph-omwenga
 
Adm proyek kontrak konstruksi.ppt
Adm proyek kontrak konstruksi.pptAdm proyek kontrak konstruksi.ppt
Adm proyek kontrak konstruksi.ppt
AdibaBaves18
 
Taxation of Damages- "Damages paid for Breach of Contract to attract GST"
Taxation of Damages- "Damages paid for Breach of Contract to attract GST"Taxation of Damages- "Damages paid for Breach of Contract to attract GST"
Taxation of Damages- "Damages paid for Breach of Contract to attract GST"
EquiCorp Associates
 
Liquidated damages contracts
Liquidated damages   contractsLiquidated damages   contracts
Liquidated damages contracts
Bhushan Goyal
 
CONSTRUCTION AND ENGINEERING LAW: THE INTERPRETATION AND APPLICATION OF DEMAN...
CONSTRUCTION AND ENGINEERING LAW: THE INTERPRETATION AND APPLICATION OF DEMAN...CONSTRUCTION AND ENGINEERING LAW: THE INTERPRETATION AND APPLICATION OF DEMAN...
CONSTRUCTION AND ENGINEERING LAW: THE INTERPRETATION AND APPLICATION OF DEMAN...
Werksmans Attorneys
 
Bonds
BondsBonds
RFP and Negotiation Best Practices.pdf
RFP and Negotiation Best Practices.pdfRFP and Negotiation Best Practices.pdf
RFP and Negotiation Best Practices.pdf
Taralee Zimmerman
 
PRC Contract Law Principles and Risk Management in Contract Drafting
PRC Contract Law Principles and Risk Management in Contract DraftingPRC Contract Law Principles and Risk Management in Contract Drafting
PRC Contract Law Principles and Risk Management in Contract Drafting
RHKLegal
 
2 claims under new fidic
2 claims under new fidic2 claims under new fidic
2 claims under new fidic
AhmetArslan47
 
Rob Tolley London - Construction Surety Bonds
Rob Tolley London - Construction Surety BondsRob Tolley London - Construction Surety Bonds
Rob Tolley London - Construction Surety Bonds
Rob Tolley
 
Pp2 p5
Pp2   p5Pp2   p5
Pp2 p5
Shze Hwa Lee
 
Wind_Energy_Law_2014_Amanda James_Overcoming Wind Energy Project Financing Ob...
Wind_Energy_Law_2014_Amanda James_Overcoming Wind Energy Project Financing Ob...Wind_Energy_Law_2014_Amanda James_Overcoming Wind Energy Project Financing Ob...
Wind_Energy_Law_2014_Amanda James_Overcoming Wind Energy Project Financing Ob...
Amanda James
 

Similar to CLI ARTICLE ON SUBCONTRACTING (20)

Subcontract Clauses.PPTX
Subcontract Clauses.PPTXSubcontract Clauses.PPTX
Subcontract Clauses.PPTX
 
Business laws
Business lawsBusiness laws
Business laws
 
Recent Trends In Guarantees
Recent Trends In GuaranteesRecent Trends In Guarantees
Recent Trends In Guarantees
 
Clause 4.2 Performance Security-Understanding Clauses in FIDIC ‘Conditions of...
Clause 4.2 Performance Security-Understanding Clauses in FIDIC ‘Conditions of...Clause 4.2 Performance Security-Understanding Clauses in FIDIC ‘Conditions of...
Clause 4.2 Performance Security-Understanding Clauses in FIDIC ‘Conditions of...
 
Loan transfer
Loan transferLoan transfer
Loan transfer
 
C ps, css, rep & warranties
C ps, css, rep & warrantiesC ps, css, rep & warranties
C ps, css, rep & warranties
 
Be aware of the legal consequences of issuing guarantee cheques in uae
Be aware of the legal consequences of issuing guarantee cheques in uaeBe aware of the legal consequences of issuing guarantee cheques in uae
Be aware of the legal consequences of issuing guarantee cheques in uae
 
Clause 16 suspension
Clause 16 suspensionClause 16 suspension
Clause 16 suspension
 
Specific performance, can parties contract out
Specific performance, can parties contract outSpecific performance, can parties contract out
Specific performance, can parties contract out
 
Adm proyek kontrak konstruksi.ppt
Adm proyek kontrak konstruksi.pptAdm proyek kontrak konstruksi.ppt
Adm proyek kontrak konstruksi.ppt
 
Taxation of Damages- "Damages paid for Breach of Contract to attract GST"
Taxation of Damages- "Damages paid for Breach of Contract to attract GST"Taxation of Damages- "Damages paid for Breach of Contract to attract GST"
Taxation of Damages- "Damages paid for Breach of Contract to attract GST"
 
Liquidated damages contracts
Liquidated damages   contractsLiquidated damages   contracts
Liquidated damages contracts
 
CONSTRUCTION AND ENGINEERING LAW: THE INTERPRETATION AND APPLICATION OF DEMAN...
CONSTRUCTION AND ENGINEERING LAW: THE INTERPRETATION AND APPLICATION OF DEMAN...CONSTRUCTION AND ENGINEERING LAW: THE INTERPRETATION AND APPLICATION OF DEMAN...
CONSTRUCTION AND ENGINEERING LAW: THE INTERPRETATION AND APPLICATION OF DEMAN...
 
Bonds
BondsBonds
Bonds
 
RFP and Negotiation Best Practices.pdf
RFP and Negotiation Best Practices.pdfRFP and Negotiation Best Practices.pdf
RFP and Negotiation Best Practices.pdf
 
PRC Contract Law Principles and Risk Management in Contract Drafting
PRC Contract Law Principles and Risk Management in Contract DraftingPRC Contract Law Principles and Risk Management in Contract Drafting
PRC Contract Law Principles and Risk Management in Contract Drafting
 
2 claims under new fidic
2 claims under new fidic2 claims under new fidic
2 claims under new fidic
 
Rob Tolley London - Construction Surety Bonds
Rob Tolley London - Construction Surety BondsRob Tolley London - Construction Surety Bonds
Rob Tolley London - Construction Surety Bonds
 
Pp2 p5
Pp2   p5Pp2   p5
Pp2 p5
 
Wind_Energy_Law_2014_Amanda James_Overcoming Wind Energy Project Financing Ob...
Wind_Energy_Law_2014_Amanda James_Overcoming Wind Energy Project Financing Ob...Wind_Energy_Law_2014_Amanda James_Overcoming Wind Energy Project Financing Ob...
Wind_Energy_Law_2014_Amanda James_Overcoming Wind Energy Project Financing Ob...
 

CLI ARTICLE ON SUBCONTRACTING

  • 1. Proposals for a subcontractor’s escape from a conditional clause Antonios Dimitracopoulos Bin Shabib & Associates, UAE Types of conditional clauses Conditional clauses can be broadly divided into two categories, namely ‘pay when paid’ and, ‘pay if paid’ clauses. Pay when paid clauses generally contain a condition such that payment by the main contractor to the subcontractor will be dependent upon payment being first received by the main contractor from the employer. The main purpose of a pay when paid clause is to defer payment to a point in time The common practice is that the main contractor will contractually delegate various elements of its works to specialist subcontractors. Such subcontractors may be sourced and chosen by the main contractor or may be specifically nominated by the employer. The UAE Civil Code1 at Article 8902 expressly provides for the right of the main contractor to subcontract, provided there are no contractual terms preventing this in the main contract. Therefore, main contractors are potentially exposed to making payments to their subcontractors when they have not themselves received the corresponding payments from the employer. Main contractors, therefore, often include conditional payment clauses in subcontracts so as to confer payment related risks onto the subcontractor. that is determined by a specific event, namely payment by the employer to the contractor. The occurrence of pay if paid clauses in the UAE is relatively uncommon. In general, whenever pay if paid clauses are included in subcontracts internationally, they may amount to specific wording that aims to clarify that a shift of the risk of non-payment has been agreed to. Instances of pay if paid clauses, identified in primarily US cases, can be focused particularly on clearly and aggressively reflecting the parties’ intentions. CONSTRUCTION LAW INTERNATIONAL Volume 10 Issue 2 June 2015 25
  • 2. SUBCONTRACTOR’S ESCAPE As indicated above, the intention of pay if paid clauses depends on the eventuality rather than on deferring the timing of payment and to shift the risk of non-payment from the main contractor to the subcontractor. UAE statutory law background to conditional payment structures in construction UAE law provides a protective barrier for the employer and confirms, in the Muqawala section of the UAE Civil Code, Article 891, that no claim may be addressed by the subcontractor to the employer, save for instances of assignment.3 This being the position, one must ask what consideration does the subcontractor enjoy in return for this unenviable shift in risk-taking that conditional clauses impose? For conditional clauses to have a fair sense of purpose in a subcontract, the answer to that question must revolve around the following: • the main contractor is obliged to adopt the subcontractor’s claims for payment as if the claims were its own; • to the extent it considers the claims valid, the main contractor must then pursue them with the employer, again as if they were its own; and • any failure to do so should prohibit the main contractor from relying on any conditional clause, thus rendering it directly accountable to the subcontractor. In terms of legal authority, the concept of conditional payments seems to fall squarely within the ambit of Part 3, Section 1 of the UAE Civil Code, relating to ‘Dispositions conditional by suspension or deferment’,4 Article 428 of which supports the view that if the performance of an obligation is subject to a condition, then efforts must be made for that condition to be observed.5 It is not relevant how much time has passed since payment to the subcontractor became due, but rather what can be proven to have taken place during such time. This would appear to be a more dominant driver in determining the operation of a conditional clause under UAE law. By contrast, if it can be shown that no demonstrable efforts (in the context of Article 428) have been made to observe the condition, then it would be arguable under UAE law that the main contractor can no longer rely on a conditional pay when paid clause and that to effectively avoid making payment to the subcontractor, it would have to resort to more substantive defences. As will be seen below, recent UAE jurisprudence has indicated that, in the presence of a conditional clause, a claim against the main contractor based purely on a breach of the subcontract for non-payment is likely to fail. UAE jurisprudence Whilst many disputes arising out of subcontracts will be referred to private and confidential arbitration, there have been a few instances where an arbitration clause was absent and litigation ensued. From the cases readily reported, save one case in 1995 where a distinction was made by the Dubai courts on whether a project had been completed or not6 before a conditional payment clause could be relied upon, most subsequent cases7 upheld the validity of a pay when paid clause and rejected the claims filed by the subcontractors on the basis of them being premature.Inonesuchcase,8 theapplication of conditional payment clauses in a subcontract was analysed as follows: • the contractor imposed a condition that payments to the subcontractor would be paid when such moneys from the employer were paid; • this is an obligation suspended until the conditional fact materialised; and • the subcontractor, therefore, did not have the right to claim the balance of its dues until the condition was met, that is, payment was received by the main contractor from the employer. In all these cases, the subcontractor’s claims were made on the simple basis of a breach of contract for non-payment. They were not based on an argument that the true breach was that the main contractor had failed to pursue fully the subcontractor’s claims against When faced with a conditional payment clause, the subcontractor’s main strategy in pursuing its claims against the main contractor is one of timing 26 CONSTRUCTION LAW INTERNATIONAL Volume 10 Issue 2 June 2015
  • 3. the employer. Nor were they based on the employer having rejected such claims, thus containing the dispute strictly between the main contractor and the subcontractor. The subcontractor’s position was countered by a straightforward application of Article 420 of the UAE Civil Code,9 in that the condition precedent (of payment by the employer) had not yet occurred. Alternative bases for the subcontractor to pursue its claims In light of the above, and given the factors set out below, we explore two alternative bases upon which a subcontractor can successfully pursue its claims against the main contractor, including whether the timing of any actions it needs to take to achieve this: • pay if paid clauses are relatively rare in the UAE; • pay when paid clauses defer the timing of payment; • the UAE Civil Code acknowledges that some effort must be made for a condition to materialise; and • that the consideration that the subcontractor must enjoy is the main contractor’s obligation of pursuing the subcontractor’s claims. Direct payment agreements with the employer Although the ability for subcontractors to successfully negotiate the terms of their subcontract are usually very limited, we have seen instances where nominated subcontractors managed to extract a direct payment obligation by the employer, at least for certified amounts, thus bypassing the main contractor. This option is also envisaged by UAE law, in the Muqawala section of the Civil Code,10 as a possible exception to be executed by way of assigning the obligation to pay the subcontractor from the contractor to the employer. Two issues are of note in instances where direct payment mechanisms have been attempted in the UAE: • thestandardobligationofthemaincontractor to effect payment to the subcontractor (on a pay when paid basis) is often not removed from either of the two subcontracts; and • court proceedings that are normally brought by the subcontractor against both the employer and the main contractor have resulted in the court ordering the subcontractor to proceed first to arbitration under the subcontract against the main contractor and, if that were to fail or result in non-payment, then – and only then – could the subcontractor proceed in court against the employer under the direct payment agreement. Direct payment agreements are seldom well-coordinated with the contents of either the main contract or the subcontract and commonly serve as a tool for the employer to deflect liability for the subcontractor’s payments onto the main contractor and vice versa. Lack of pursuit of subcontractor’s claims A further option for the subcontractor is to argue that the true breach lies in the main contractor failing to pursue the subcontractor’s claims against the employer to the fullest extent permissible by law. The instances where the subcontractor could legitimately argue this include: • when the employer has rejected the subcontractor’s claim, the main contractor has not accepted such rejection, but has failed to pursue the matter by way of a dispute resolution process or otherwise; or • when the employer has deferred payment to an indefinite point in time that can no longer be considered reasonable and the main contractor again fails to pursue the matter whether by way of a dispute resolution process or otherwise. Article 428 of the UAE Civil Code sets out the degree to which fulfilment of the condition must be pursued. This lends itself to an argument that a main contractor’s failure to pursue the subcontractor’s claims could effectively amount to a failure to observe the condition (of payment by the employer) to the maximum degree possible. In the presence of a conditional clause, it is… unwise for the subcontractor to commence legal proceedings against the main contractor on the simple basis of a debt collection exercise CONSTRUCTION LAW INTERNATIONAL Volume 10 Issue 2 June 2015 27
  • 4. SUBCONTRACTOR’S ESCAPE One must be mindful of the fact that main contractors would commonly be reluctant to start a dispute resolution process against an employer purely in order to pursue their subcontractors’ claims. In demonstrating such reluctance, the main contractor may argue: • that at the stage the subcontractor’s action commenced, it would be unreasonable for it (the main contractor) to have commenced legal proceedings; or • that this may be supported by reference to various commercial or contractual considerations. Whichever option the main contractor adopts, it is likely that if pursuit of the subcontractor’s claim is to be argued as a condition precedent for any conditional SEQUENCE TIMING S/C’s REQUEST/DEMAND BASIS A When invoices become overdue. Payment of its outstanding invoices/ dues. Contractual. B When negative reply is received from main contractor (MC) on first request. Evidence of inclusion of its work in monthly invoices to Employer (E). Contractual/correspondence based. C Once evidence of inclusion in monthly invoices/final statement of accounts has been provided. Evidence of rejection of payment by E. Contractual/correspondence based. D Pay when paid (PWP): once confirmation of E’s rejection and MC’s agreement to this is obtained. Payment of dues by MC. Legal: impossibility of condition, Article 423 of Civil Code. E Pay if paid (PIP)/PWP: whether or not E has rejected payment & whether or not MC has contested any rejection by E. Evidence of pursuit of payment. Legal: lack of pursuit, Articles 420 and 428 of Civil Code. F Once the scope of subcontractor’s (SC) work has been completed. Evidence of pursuit of payment. Legal: lack of pursuit, Articles 420 and 428 of Civil Code. G Again when the project has been handed over. Evidence of pursuit of payment. Legal: lack of pursuit, Articles 420 and 428 of Civil Code. H Again when the defects liability period has expired. Evidence of pursuit of payment. Legal: lack of pursuit, Articles 420 and 428 of Civil Code. I When negative reply is received from MC on the above request. Evidence of a legal notice issued for amounts inclusive of the subcontractor’s dues. Legal: Lack of pursuit, Articles 420 and 428 of Civil Code. J When the deadline of a legal notice expires. Evidence of legal proceedings having been commenced. Legal: Lack of pursuit, Articles 420 and 428 of Civil Code. clause to be relied upon, then such condition could be easily satisfied in most instances, save for the case of the main contractor formally commencing legal proceedings against the employer. Employer’s outright rejection of a subcontractor’s claim As indicated above, instances of an outright rejection by the employer of a main contractor’s claim that includes or relates to the subcontractor’s works would convert the question of when payment would be made to a definite non-payment. In terms of how this can be accommodated within the confines of 28 CONSTRUCTION LAW INTERNATIONAL Volume 10 Issue 1 March 2015
  • 5. UAE law, Articles 420–428 of the UAE Civil Code deal with ‘Dispositions conditional by suspension or deferment’, essentially relating to conditional clauses. The main contractor’s options in instances of outright rejection by the employer would be to: • challenge the merits of the subcontractor’s entitlement (rather than simply its timing) and adopt arguments raised by the employer/engineer; • challenge the merits of the subcontractor’s entitlement (rather than simply its timing) and produce its own arguments for doing so; or • challenge the employer’s rejection, pursuing claims that would include those of the subcontractor. Which option the main contractor adopts can be of critical relevance to the application of either a pay when paid clause or a pay if paid clause. Pay when paid clauses are based on a presumption that payment would eventually be made. They would, therefore, become inapplicable if the employer refused to pay, for the simple reason that for the main contractor to rely on them, it would have to unilaterally convert the condition of ‘when’ to a condition of ‘if/whether’. Timing as a key factor to a subcontractor’s strategy When being faced with a conditional payment clause, the subcontractor’s main strategy in pursuing its claims against the main contractor is one of timing. Therefore, a subcontractor that is deprived of its dues should sequence its approach to a conditional payment clause by documenting its requests as follows. Once the main contractor is forced to file a legal action against the employer, the subcontractor’s claims against the main contractor are effectively carried over onto an action against the employer. Whilst the subcontractor can have little control over suchproceedings(unlessthemaincontractor encourages them to assist), the conditional clause will have been given the purpose and substance that the parties intended. On the assumption that an award or judgment is eventually issued and, despite the main contractor’s perceived best efforts, the subcontractor’s claims (or any part thereof) are not awarded, the question arises whether this would be the end of the road for the subcontractor. The answer to this question would depend a lot more on what the reason is behind the employer’s exoneration, rather than on whether the subcontract contained a pay if paid or a pay when paid clause. Conclusion In the presence of a conditional clause, it is generally accepted that it is unwise for the subcontractor to commence legal proceedings against the main contractor on the simple basis of a debt collection exercise as it is unlikely to succeed. Ironically, the more unopposed (by the main contractor) a subcontractor’s claim is, the more difficult it is to control the payment process and the more hindered it is by a conditional clause. Conversely, any direct challenge to its claims by the main contractor may block the triggering of a conditional clause, thus making the dispute resolution process an affair that is confined solely between the main contractor and the subcontractor. Finally, the question of whether a subcontractor can pursue its claims against the main contractor, even after the employer has been exonerated of any liability, will depend more on the reasons behind this, rather than on the nature of the conditional clause. Notes 1 Federal Law No 1/1987. 2 An English translation of which states: ‘(1) A contractor may entrust the performance of the whole or part of the work to another contractor unless he is prevented from so doing by a condition of the contract, or unless the nature of the work requires that he do it in person. (2) The first contractor shall remain liable as towards the employer.’ 3 An English translation states that: ‘Article 891: A sub-contractor shall have no claim against the employer for anything due to him from the first contractor unless he has made an assignment to him against the employer.’ 4 Arts 420–428 of the Civil Code. 5 An English translation states: ‘Article 428: A Condition must be observed as far as is possible.’ 6 Dubai Court of Cassation Case No 281 of 1995: the distinction related to an obligation by the main contractor to pay the subcontractor, despite a conditional clause, if the project has been completed. 7 Dubai Court of Cassation Case No 267 of 2007, Dubai Court of Cassation Case No 83 of 2009. 8 Dubai Court of Cassation Case No 240 of 2006. 9 An English translation of which provides that: ‘Article 420: A Condition is a future matter upon the existence or absence of which the full effectiveness (of a disposition) depends.’ 10 Art 891, as previously mentioned. Antonios Dimitracopoulos MCIArb is a partner with Bin Shabib & Associates, practising in the UAE since 1995. He is dually qualified as a solicitor of the Senior Courts of England & Wales and a Greek attorney at law and a registered arbitrator with the Dubai International Arbitration Centre. His practice focuses on all aspects of dispute resolution within the local construction industry, often acting for subcontractors. He has rights of audience before the DIFC courts and extensive experience in both UAE litigation and arbitration. He can be contacted at antonios. dimitracopoulos@ bsa.ae. CONSTRUCTION LAW INTERNATIONAL Volume 10 Issue 2 June 2015 29