Related Pages
What is Decommissioning?
Decommissioning begins immediately following final and permanent closure and continues ideally to the point of leaving a clear site where the facility had once stood. The decommissioning process incorporates some or all of the following activities: the safe management of nuclear materials held in the facility, the safe management of radioactive and other wastes, decontamination, plant dismantling, demolition and site remediation.
Which Facilities Need to be Decommissioned?
All facilities within the commercial nuclear fuel cycle will eventually need to be decommissioned following their permanent closure. In addition there are many nuclear research facilities and defense related establishments that will require decommissioning.
As of September 2001, over 90 commercial power reactors, 50 fuel cycle facilities, around 100 mines and more than 250 research facilities have been retired from operation. Many are currently being or have successfully been decommissioned.
How is a Nuclear Facility Decommissioned?
The decommissioning of a nuclear facility is generally categorized into a number of stages. The first stage is plant cleanout. This generally begins immediately following shutdown. The next stages will depend on what type of facility is being decommissioned.
The next stage for all facilities is decontamination, which incorporates the removal of contamination from surfaces of facilities or equipment. Following decontamination, equipment within the facility may be dismantled. Likewise, equipment within the building(s) on the non-radioactive side of the facility (such as offices, turbine halls) can be removed for possible re-use, and the building(s) themselves demolished.
Demolition and Site Clearance
In practice, the extent to which buildings are demolished and the site cleared, following decontamination and dismantling, is dependent on the decommissioning strategy and in some cases, the owner's purposes of re-using the site following delicensing. For example, it may be possible to re-use some buildings on site for non-nuclear purposes rather than have them demolished.
De-licensing and Release of the Site to Alternative Use
Once it has been demonstrated that the site is safe and that radiation levels are below the national regulatory requirements, the operating licence is terminated and the site is then available for re-use.
Note that the time taken to complete these phases, as well as the period in between each phase, can vary considerably depending on national policy. The issue of timescales associated with the decommissioning process is discussed in the following section.
Note also that where there is more than one plant or building within the facility being decommissioned the different phases may occur at different timescales. Thus non-active buildings may move through to demolition and site clearance relatively quickly after shutdown whereas some buildings could be left for long-term storage.
Timing of the Decommissioning Approach
Decommissioning strategies can vary considerably in timescale.
Two main options are available, namely a move to early dismantling, termed "Early Site Release" (or "DECON" in the US) or deferral of one or more phases, an option called "Safestor(e)".
There is no "right" or "wrong" approach. In practice, individual national policy and the owner's strategy determines which strategy is adopted. (view a "A Decommissioning Strategy" to see which factors are taken into account when deciding which approach is suitable)
A third decommissioning option, termed "Entomb" has been defined in the US.
This option refers to the encasement of the nuclear facility in a long-lived substance, such as concrete. The facility is appropriately maintained and monitored until the radioactivity has decayed to a level which permits termination of the site licence.
In practice, however, the licensees for nuclear facilities undergoing decommissioning have not adopted the entombment option.
Further Reading:Decommissioning Nuclear Facilities